Search This Blog

Translate the Site to your native language

Showing posts with label unauthorised construction. Show all posts
Showing posts with label unauthorised construction. Show all posts

Monday, 28 September 2026

A promoter cannot materially alter a real-estate project, introduce additional construction or substantially modify common/open/recreational areas contrary to the project plan and disclosures on the basis of which allottees purchased their units, without complying with the consent and other requirements imposed by Section 14 of RERA.

 

Parshvadhara Complex ABCD Co-operative Housing Society Ltd. v. M/s Parshwanath Developers & Ors.

Maharashtra Real Estate Appellate Tribunal (MahaREAT), Mumbai
Appeal Nos.: AT006000000345557 & AT006000000345563 of 2024
Order dated: 7 September 2026

This is a significant MahaREAT ruling on unauthorised alteration of a sanctioned project, additional construction, protection of open/common areas, and the requirement of allottee consent under Section 14 of RERA. The Tribunal ordered demolition of an additional building constructed after a revised sanction, imposed a ₹10 lakh penalty on the promoters, and directed restoration of the project substantially in accordance with the original 2015 plan.

1. Background of the dispute

The dispute concerned the Parshvadhara Complex at Belavali, Ambernath, District Thane, Maharashtra.

The project covered approximately 3,870 sq. metres. The original 2015 sanctioned layout contemplated Wings A, B, C and D and was represented to purchasers through the project's documents and disclosures.

The Tribunal noted that:

  • Wings B, C and D received Occupation Certificates on 29 January 2019.

  • Wing A received its Occupation Certificate on 7 October 2022.

  • Thus, the project contemplated under the original 2015 plan had effectively been completed by October 2022. 

The controversy arose because the promoters subsequently obtained a revised sanction dated 2 July 2021, introducing an additional Building E.

The Society's case was that this additional building was introduced without informing or obtaining the requisite consent of the existing allottees, and that the additional construction adversely affected open and recreational areas shown in the original project plan. 


2. What was the Society's objection?

The Society contended that purchasers had bought their apartments on the basis of the 2015 sanctioned plan, brochure and other project disclosures.

Those documents showed certain areas as:

  • playground;

  • garden;

  • children's playground;

  • recreation ground; and

  • other open/common areas.

The subsequent construction of Building E altered the development originally represented to the purchasers.

The Society therefore argued that the promoter could not unilaterally change the project after purchasers had acquired rights on the basis of the original disclosures.


3. Proceedings before MahaRERA

The Society issued a legal notice on 24 January 2022.

It subsequently approached MahaRERA on 21 April 2022, challenging the additional construction and seeking restoration of the affected areas and amenities.

The dispute ultimately reached MahaREAT through two connected appeals:

  • AT006000000345557 of 2024

  • AT006000000345563 of 2024

The Tribunal heard the Society's appeal as well as the promoters' challenge.


4. Central legal question

The principal question was:

Can a promoter introduce an additional building or materially alter the sanctioned/project plan after purchasers have acquired their apartments on the basis of an earlier disclosed plan, without obtaining the consent required under RERA?

MahaREAT answered this question against the promoters in the circumstances of the case.


5. Section 14 of RERA — the heart of the case

The decision is principally important for Section 14 of the RERA Act.

Section 14 requires the promoter to adhere to the sanctioned plans and specifications and regulates alterations to the sanctioned plan.

In particular, material alterations require the requisite consent of the allottees.

The Tribunal's approach was that the promoter cannot treat a subsequent planning permission or revised sanction from a planning authority as automatically giving it the right to alter the project vis-à-vis purchasers.

Important distinction

There are effectively two separate questions:

Planning authority approval

versus

RERA compliance vis-à-vis allottees

Obtaining revised permission from a municipal/planning authority does not, by itself, eliminate the promoter's obligations towards purchasers under RERA.

That distinction is one of the most useful aspects of this ruling.


6. Why was Building E problematic?

The Tribunal considered the original project documents and the subsequent development.

The original 2015 plan had disclosed a particular configuration of the project.

The later Building E was not merely a minor modification.

According to the Tribunal's findings, its construction affected the open and recreational areas that had been represented to the purchasers.

Therefore, the issue was not simply:

“Did the promoter obtain a revised sanction?”

Instead, it was:

“Could the promoter materially change the project and the rights/amenities represented to the existing allottees without complying with RERA?”

The Tribunal concluded that the answer was no. 


7. The Tribunal's most consequential direction — demolition

MahaREAT directed the promoters to:

Demolish Building E

The demolition was to be carried out:

  • at the promoters' own expense, and

  • within 90 days.

This is an unusually strong remedial direction because the Tribunal did not merely impose a monetary penalty.

It required restoration of the project to the position contemplated by the earlier sanctioned plan.


8. Restoration of open and recreational areas

The Tribunal further directed restoration of the affected areas in accordance with the 2015 sanctioned plan, brochure and other disclosures made to the allottees.

The areas specifically referred to included:

  • playground;

  • garden;

  • children's playground;

  • recreation ground; and

  • other open spaces.

This is important because it recognises that a purchaser's rights under RERA can extend beyond the apartment itself.

The project configuration and promised common amenities can also form part of the purchaser's legitimate contractual/statutory expectations.


9. Conveyance of the project land

Another significant direction was concerning conveyance.

The promoters were directed to execute conveyance of the 3,870-square-metre project land, common areas and open spaces in favour of the Society within 90 days, subject to the promoters' right to dispose of any remaining flats. 

This demonstrates the Tribunal's broader approach: the dispute was not confined to Building E but also concerned the Society's rights over the project and common areas.


10. Additional directions regarding Wing D

The Tribunal also directed the promoters to construct/complete facilities associated with D-Wing, including:

  • meter room;

  • parking; and

  • society office,

in accordance with the 2015 plan. 

This reinforces the principle that the promoter must implement the project substantially in accordance with the commitments and disclosures on the basis of which purchasers acquired their units.


11. Water connections

The Tribunal directed the promoters to pursue the concerned authorities and obtain 30 water connections within 90 days.

This was another indication that the Tribunal was concerned not merely with the legality of Building E but with the completion of the project-related obligations affecting the Society and residents.


12. Completion certificate

The promoters were further directed to obtain the completion certificate in accordance with the 2015 sanctioned plan and provide it to the Society.

This is particularly significant in the context of the Tribunal's direction to restore the project to the original sanctioned configuration.


13. ₹10 lakh penalty

MahaREAT imposed a ₹10 lakh penalty under Section 61 of RERA on the promoters.

Section 61 deals with penalties for contravention of provisions of the Act for which no separate penalty is provided.

The penalty was directed to be paid within 30 days. 

Thus, the Tribunal imposed both:

Corrective relief

Demolition/restoration/conveyance/completion measures

and

Penal consequences

₹10 lakh penalty under Section 61.


14. Outcome of the appeals

The Tribunal:

  • dismissed the promoters' appeal; and

  • partly allowed the Society's appeal.

The MahaREAT therefore modified the Authority's order and issued the additional directions described above. 


15. Ratio Decidendi

The principle emerging from the decision can be stated as:

A promoter cannot materially alter a real-estate project, introduce additional construction or substantially modify common/open/recreational areas contrary to the project plan and disclosures on the basis of which allottees purchased their units, without complying with the consent and other requirements imposed by Section 14 of RERA.

A further important proposition is:

Approval of a revised plan by a planning authority does not, by itself, absolve the promoter from complying with its statutory obligations towards allottees under RERA.


16. Why this case is important for Apartment Owners' Associations

This decision is particularly useful for Co-operative Housing Societies, Apartment Owners' Associations and Resident Welfare Associations.

Where a developer proposes:

  • an additional tower;

  • an additional building;

  • construction on an open area;

  • reduction of recreational space;

  • conversion of a garden/playground;

  • alteration of promised amenities; or

  • substantial modification of the original layout,

the Society can examine whether the proposal is consistent with:

  1. the sanctioned plan;

  2. the Agreement for Sale;

  3. the brochure;

  4. the allotment documents;

  5. the RERA disclosures;

  6. the sanctioned layout;

  7. the common-area representations; and

  8. the consent requirements under Section 14.


17. A crucial legal distinction

The judgment should not be read as saying that every change in a project is prohibited.

The real question is whether the proposed alteration is:

Minor / already contemplated

or

Material / beyond what purchasers agreed to.

For example, a change that is already expressly contemplated by the Agreement for Sale and sanctioned project documents may raise a different issue.

But where the promoter seeks to introduce a material additional development that changes the project and affects areas or amenities represented to existing purchasers, Section 14 becomes particularly important.


18. Comparison with Raintree Boulevard

This case is especially useful when read with the Raintree Boulevard Apartment Owners Association v. L&T Realty Developers Ltd. decision from Karnataka RERA.

The two decisions illustrate an important proposition:

SituationRERA consideration
Change already contemplated/agreed in project documentsFresh consent may not necessarily be required
Material change beyond what was agreed/disclosedSection 14 consent requirements become important
Additional construction affecting promised open/common areasStronger case for requiring allottee protection/consent
Revised municipal sanction obtainedDoes not automatically eliminate RERA obligations

19. Practical takeaway for promoters

Before undertaking additional construction, a promoter should carefully examine:

Original sanctioned plan → RERA registration documents → Agreement for Sale → brochure/project disclosures → common-area commitments → Section 14 → required allottee consent

A subsequent revised sanction from the planning authority should not be treated as a complete answer to the RERA question.


20. Practical takeaway for homebuyers/Societies

For a Society challenging additional construction, the strongest documentary evidence would ordinarily include:

  • original sanctioned layout;

  • revised sanctioned layout;

  • RERA registration documents;

  • sanctioned building plans;

  • brochure;

  • Agreement for Sale;

  • allotment documents;

  • photographs/site plans;

  • records showing the original open/recreational areas;

  • correspondence with the promoter;

  • Society resolutions; and

  • evidence concerning consent or absence of consent.

The comparison between the original and revised plans can be particularly important.


21. Key RERA provisions

Section 14 — Adherence to sanctioned plans

The principal provision in the case concerning alterations to the sanctioned/project plan.

Section 61 — Penalty

Used by MahaREAT to impose the ₹10 lakh penalty for the promoter's contraventions.

Sections concerning common areas/conveyance

The Tribunal's directions concerning conveyance and restoration also demonstrate the broader statutory framework protecting allottees and their rights in relation to the project and common areas.


Final legal takeaway

Parshvadhara Complex ABCD Co-operative Housing Society Ltd. v. M/s Parshwanath Developers & Ors. is a strong MahaREAT authority against unilateral material alteration of an RERA-registered project. The Tribunal found that the promoters could not introduce Building E, affecting areas represented as open and recreational spaces, without complying with the protections available to existing allottees. It therefore ordered demolition of the additional building, restoration of the original open spaces, conveyance-related steps, completion of promised facilities, 30 water connections, and a ₹10 lakh Section 61 penalty. 


Tripura High Court Denies Writ Relief for Suppression of Pending T-RERA Proceedings, Imposes ₹40,000 Costs on Homebuyers

 

Kishore Roy Acharjee & Ors. v. State of Tripura & Ors.

Tripura High Court | W.P.(C) No. 437 of 2026 | Decided: 8 September 2026

This is a significant RERA-related writ decision concerning parallel proceedings before T-RERA and the municipal authorities, suppression of material facts, election of remedies, and the scope of discretionary writ jurisdiction.

1. Facts of the case

The petition was filed by four purchasers of ground-floor units in “The Royal Peace Apartment” at Battala, Agartala.

The petitioners complained about certain constructions allegedly made by the developer beyond the sanctioned building plan, principally:

  • toilets constructed on the northern and southern sides over drains/open areas; and

  • a brick-wall/tin-shed guard room allegedly obstructing access.

The petitioners sought intervention of the High Court for removal/demolition of the allegedly unauthorised constructions and consequential reliefs.

2. Proceedings before T-RERA and Municipal Authority

An important aspect of the case was that the petitioners had already pursued remedies concerning the same dispute before:

  • the Tripura Real Estate Regulatory Authority (T-RERA); and

  • the Agartala Municipal Corporation.

More importantly, an execution proceeding had also been initiated before T-RERA before the writ petition was filed.

The High Court found that this earlier T-RERA execution proceeding had not been disclosed in the writ proceedings.

3. Issue before the High Court

The principal questions were essentially:

  1. Whether the petitioners could invoke the High Court's writ jurisdiction after pursuing proceedings before T-RERA and the municipal authority concerning the same subject matter; and

  2. Whether suppression of the pending/existing T-RERA execution proceeding disentitled the petitioners from obtaining discretionary relief under Article 226 of the Constitution.

4. Finding on suppression of material facts

The Court took serious note of the petitioners' failure to disclose the earlier T-RERA proceedings.

Justice Dr. T. Amarnath Goud observed that the petitioners had not approached the Court with “clear hands.”

This was particularly significant because the undisclosed proceeding was not merely an earlier complaint—it included an execution proceeding before T-RERA, which was directly relevant to the relief sought in the writ petition.

The principle is important: a litigant seeking discretionary relief under Article 226 must make full and candid disclosure of material proceedings concerning the same dispute.

5. Election of remedies / parallel proceedings

The Court also considered the principle of election of remedies.

The petitioners had pursued proceedings before T-RERA as well as the municipal authorities and thereafter approached the High Court.

The Court considered that where a party has already elected and pursued a statutory remedy concerning the same cause of action, it cannot ordinarily seek a second parallel remedy while withholding the earlier proceedings from the constitutional court. (Live Law Biz)

Thus, the case illustrates an important distinction between:

availability of a statutory remedy and permissibility of simultaneously pursuing overlapping remedies without disclosure.

6. Ground-floor common toilet

The Court also considered the practical circumstances surrounding the disputed construction.

It noted that the common toilet was situated on the ground floor and was used by persons such as:

  • security personnel,

  • caretakers,

  • plumbers,

  • electricians, and

  • domestic workers.

The Court regarded such a facility as a basic necessity and found that the authorities were required to consider the ground realities and competing interests of other occupants before directing demolition. (LawLens)

7. Conduct of the petitioners

The respondents also brought to the Court's attention that the petitioners themselves had allegedly been using residential premises for commercial purposes, including a clinical laboratory and an eye clinic, contrary to the sanctioned use/building permissions.

The Court took this circumstance into account while considering whether the petitioners deserved discretionary relief. (PLEAD & PREJUDICE - Beyond the Brief)

Consequently, the Court was not persuaded to exercise its extraordinary writ jurisdiction in favour of the petitioners.

8. Decision

The High Court dismissed W.P.(C) No. 437 of 2026.

The Court declined to grant the requested directions relating to demolition, further proceedings and compensation.

It additionally imposed costs of ₹10,000 on each of the four petitioners, totalling ₹40,000.

The amount was directed to be paid to the High Court Bar Associations within one month, with the petitioners required to obtain receipts. (LawLens)

9. Ratio Decidendi

A party seeking discretionary relief under Article 226 must approach the High Court with complete candour and disclose all material proceedings concerning the same dispute. Where petitioners pursue parallel proceedings before a statutory authority such as RERA and a municipal authority, and subsequently invoke writ jurisdiction without disclosing a material pending execution proceeding, the Court may decline equitable relief on the grounds of suppression of material facts and abuse/parallel pursuit of remedies.

10. RERA relevance

The judgment is particularly relevant to RERA practitioners because Section 31 of the Real Estate (Regulation and Development) Act, 2016 was referred to in the case. (LawLens)

Section 31 provides the mechanism by which an aggrieved person may file a complaint before the Real Estate Regulatory Authority.

The case therefore demonstrates that although RERA provides a specialised statutory mechanism, parties must also consider the consequences of pursuing overlapping proceedings before RERA, municipal authorities and constitutional courts.

11. Practical impact for homebuyers and promoters

The decision carries two important lessons.

For homebuyers:
Before approaching the High Court, all earlier RERA complaints, execution proceedings, municipal proceedings and orders concerning the same dispute should be fully disclosed.

For promoters:
Where a homebuyer invokes multiple forums concerning substantially the same grievance, the promoter can raise the issue of parallel proceedings, election of remedies and suppression of material facts, particularly where an existing RERA proceeding has not been disclosed.

12. One-line legal takeaway

A litigant who pursues parallel statutory proceedings and suppresses a material RERA proceeding may be denied discretionary writ relief, even where the underlying grievance concerns alleged unauthorised construction.

The judgment was delivered on 8 September 2026 in W.P.(C) No. 437 of 2026, and has been reported as 2026 LLBiz HC (TRI) 7 / 2026 Supreme (Online) (Tri) 390. (Supreme Today AI)