Gurugram RERA Awards Rs 11.24 Lakh Compensation to Homebuyers in S.S. Group Case
Gurugram: The Haryana Real Estate Regulatory Authority (HRERA), Gurugram has awarded Rs 11.24 lakh in compensation to homebuyers Shashi Rastogi and Colonel Rajendra Kumar Rastogi (Retd.) in a dispute involving S.S. Group Pvt. Ltd. and its The Leaf project in Gurugram.
The order was passed on September 11, 2026, in Complaint No. 2934 of 2025 by Adjudicating Officer Rajender Kumar. The case concerned the buyers' claim for compensation following the developer's failure to deliver their residential unit within the agreed period.
Possession was due in September 2016
The homebuyers had booked a unit in Tower-1 of The Leaf, located in Sectors 84-85, Gurugram, and paid approximately Rs 39.38 lakh to the developer.
Possession was contractually due on September 24, 2016, but was not delivered. The buyers subsequently sought cancellation and refund, citing, among other things, medical exigencies.
In an earlier proceeding, the HRERA Authority directed S.S. Group on October 4, 2022 to refund Rs 39.38 lakh along with 10% annual interest calculated from the respective dates of payment until refund.
RERA rejects limitation objection
The developer argued that the subsequent compensation complaint was time-barred because it was filed years after the original default and possession deadline.
The Adjudicating Officer rejected the contention that the complaint was automatically barred by limitation. The order observed that the RERA Act does not prescribe a specific period for filing a complaint seeking compensation and that the question of reasonable time must be examined in light of public policy.
The compensation proceedings were initiated in June 2025, when the homebuyers approached the Adjudicating Officer under Sections 31 and 71 of the RERA Act.
Refund and interest did not bar separate compensation claim
Another important issue was whether the earlier refund order prevented the buyers from subsequently seeking compensation.
The developer argued that compensation could not be awarded after the Authority had already ordered refund with interest.
The Adjudicating Officer rejected that argument, holding that an allottee's receipt of refund with interest does not, by itself, prevent a separate claim for compensation under Section 18 where the statutory conditions are met.
Rs 11.24 lakh compensation awarded
The Adjudicating Officer considered the buyers' claim relating to loss of property appreciation, while noting that the complainants had not produced conclusive evidence establishing a specific annual appreciation rate for the property.
The order nevertheless assessed the loss using available market-price information.
The compensation comprised:
Rs 8.74 lakh towards loss of property appreciation;
Rs 2 lakh for mental agony and harassment; and
Rs 50,000 towards litigation expenses.
The total compensation therefore came to Rs 11.24 lakh.
The amount was directed to carry 11% annual interest from September 11, 2026 until realisation.
Broader significance
The ruling addresses two issues of interest to homebuyers: whether the RERA Act imposes a fixed limitation period for compensation claims and whether a previous order granting refund and interest prevents an allottee from seeking additional compensation.
The order indicates that, in the circumstances of this case, refund with interest and compensation were treated as distinct remedies, while the question of delay was examined through the requirement that proceedings be brought within a reasonable period.
The decision therefore adds to the developing body of RERA jurisprudence concerning delayed possession, refund, compensation and the rights of homebuyers after a project fails to meet its promised delivery timeline.