Tuesday, 13 April 2021

Consumer Protection Act: Entitlement of the Allottee / Homebuyer has to be reckoned in terms of the Date of the Agreement and not the RERA Registration date.

 IN THE MATTER OF: M/s. Imperia Structures Ltd. Vs. Anil Patni and Another (Decided by Hon’ble Supreme Court of India on 02.11.2020) 

Issues: 

    1. Whether the remedies available to the consumers under provisions of the Consumer Protection Act, 1986 (“CP Act”) would be additional remedies, not barred by the coming in force of the Real Estate (Regulation and Development) Act, 2016 (“RERA Act”)? 

2. Whether the provisions of the RERA Act have made any change in the legal position with regards to remedies available to the Allottees? 

3. Whether the entitlement of the Allottee has to be reckoned in terms of the date of Agreement or the RERA registration date? 


Facts: 

    1. A Housing Scheme called “The ESFERA” in Gurgaon, Haryana was launched by the Appellant in 2011. All the Complainants booked their respective apartments by paying the requisite booking amounts and thereafter executed the Builder Buyer Agreement towards their individual units. The Agreement provided for delay due to reasons beyond the control of the Developer (Appellant) and failure to deliver possession due to Govt. Rules/Notifications, etc under the Force Majeure clause and the compensation thereof. Even after four yearsthere was no sign of Project getting completed. Thereafter, in 2017, the Project was registered with Haryana Real Estate Regulatory Authority, Panchkula (“HRERA”). 

2. The Consumer Complaint was filed by the Complainants for the delay in handing over of the possession of their respective apartments. In response, the Appellant challenged the jurisdiction of the National Consumer Dispute Redressal Commission (“National Commission”) on the ground that the Complainants/Respondents would not come within the definition of consumers. After having heard the submissions, the Commission allowed the Complaint and granted relief of refund to the Complainants/Respondents. 

3. The Appellant aggrieved by the order of the National Commission, preferred an appeal under Section 23 of the CP Act before the Hon’ble Supreme Court. Court’s Observations: 

• The Counsel for Appellants submitted that once the RERA Act came into force, all questions concerning the Project including issues relating to construction and completion thereof, would be under the exclusive control and jurisdiction of the authorities under RERA Act. The National Commission, therefore, ought not to have entertained the Consumer Complaint. Further, the Registration Certificate being valid upto 31.12.2020, the Appellant could not be said to have delayed the construction and consequently, there could be no finding that there was deficiency on part of the Appellant. The Counsel for the Respondents submitted that whether the delay occurred due to force majeure was already dealt by the National Commission and no reasonable explanation was available on record to dislodge that finding. It was further submitted that the remedy afforded by the CP Act would be an additional remedy to a consumer and such legal position remained unchained even after the enactment of the RERA Act. 

• The Court noted that conclusions drawn by the National Commission that – i) all the Complainants were consumers within the meaning of the Act; and ii) there was delay on part of the Appellant in completion the construction within time, are absolutely correct and does not call for interference of this Hon’ble Court. • While discussing various precedents, the Court observed that the Hon’ble Apex Court has consistently held that the remedies available under the provisions of the CP Act are additional remedies over and above the other remedies including those made available under any special statutes;and that the availability of an alternate remedy is no bar in entertaining a complaint under the CP Act. The Hon’ble court further observed that insofar as cases where such proceedings under the CP Act are initiated after the provisions of the RERA Act came into force, there is nothing in the RERA Act which bars such initiation. The absence of bar under Section 79 to the initiation of proceedings before a fora which cannot be called a Civil Court and express saving under Section 88 of the RERA Act, make the position quite clear. Furthermore, Section 18 itself specifies that the remedy under said Section is "without prejudice to any other remedy available". Thus, the parliamentary intent is clear that a choice or discretion is given to the allottee whether he wishes to initiate appropriate proceedings under the CP Act or file an application under the RERA Act. 

• The Court held that in the present case the apartments were booked by the Complainants in 2011-2012 and the Builder Buyer Agreements were entered into in November, 2013. As promised, the construction should have been completed in 42 months. The period had expired well before the Project was registered under the provisions of the RERA Act. Merely because the registration under the RERA Act is valid till 31.12.2020 does not mean that the entitlement of the concerned Allottees to maintain an action stands deferred. It is relevant to note that even for the purposes of Section 18, the period has to be reckoned in terms of the agreement and not the registration. Therefore, the entitlement of the Complainants must be considered in the light of the terms of the Builder Buyer Agreements and was rightly dealt with by the Commission. 

The Hon’ble Court dismissed the appeal, affirming the view taken by the National Commission.