Search This Blog

Translate the Site to your native language

Showing posts with label revised possession date. Show all posts
Showing posts with label revised possession date. Show all posts

Tuesday, 22 September 2026

Telangana REAT Holds That Extension of Project Registration Does Not Automatically Extend Contractual Possession Date

 

Telangana REAT Holds That Extension of Project Registration Does Not Automatically Extend Contractual Possession Date

Case: M/s Vasavi Realtors LLP v. Taru Trivedi & Connected Matters
Case Nos.: T.A. Nos. 17 to 47 of 2026
Forum: Telangana Real Estate Appellate Tribunal (TSREAT)
Decision: 9 September 2026

The appeals arose from 31 complaints filed by homebuyers concerning the promoter's project “Vasavi Lake City-West” at Hafeezpet, Hyderabad. The Telangana RERA had directed the promoter to pay interest for delayed possession and to complete the project and hand over possession.

Background

The homebuyers had entered into agreements of sale with Vasavi Realtors in 2022. Under those agreements, possession was to be delivered by 31 August 2024, with a six-month grace period extending the date to 28 February 2025, subject to the applicable force-majeure provision.

The promoter subsequently obtained an extension of the RERA registration of the project. It contended that this extension should also affect the possession timeline.

The homebuyers, however, approached Telangana RERA after possession was not delivered within the agreed period.

Finding of the Telangana REAT

The Tribunal rejected the contention that an extension of RERA registration automatically extends the contractual possession date.

It held, in substance, that:

Extension of registration of a project does not, by itself, extend the possession date agreed between the promoter and the homebuyer.

The Tribunal treated the Agreement of Sale as a legally enforceable contract and held that the promoter could not unilaterally alter the agreed possession date. A change in that date would require agreement between the parties.

COVID-19 defence

The promoter also sought to rely upon the COVID-19 pandemic as a justification for the delay.

The Tribunal did not accept this contention because the agreements in question were executed after the lockdown periods, and they themselves stipulated specific possession timelines. The promoter therefore could not retrospectively rely upon COVID-19 to avoid its contractual and statutory liability for delay.

Interest for delayed possession

Telangana RERA had directed the promoter to pay interest at 10.70% per annum on the amounts actually paid by the respective homebuyers, calculated from 1 March 2025 until lawful possession was handed over.

The REAT found no illegality or procedural irregularity in these directions and confirmed the orders passed by Telangana RERA.

Important RERA proposition

The judgment is useful for the proposition that:

An extension granted by RERA to the validity/registration period of a real estate project does not automatically modify the possession date contractually agreed between the promoter and the allottee.

Thus, regulatory extension of project registration and contractual extension of possession are distinct matters. Unless the possession date is validly altered with the consent of the parties or otherwise justified under the governing contractual/statutory provisions, the original contractual date continues to be relevant for determining delay under Section 18 of the RERA Act.

Final outcome

The Telangana REAT dismissed all 31 appeals filed by Vasavi Realtors LLP and upheld Telangana RERA's orders directing payment of delay interest and completion/handing over of the project.

Sunday, 16 May 2021

That Just because home buyers continued to pay even after the promised possession date had lapsed, they had not "acquiesced" and not consented to the delay in possession

 In the Matter of Saurabh Mehrotra Vs.CCI Projects Pvt Ltd Complaint no.CC006000000078611  decided on 06.08.2020  Before Maharashtra Real Estate Regulatory Authority.


x

  • The Rivali Park project, rechristened as Wintergreen, has been delayed for more than three years. The developer CCI Projects Ltd had sought last mile funding for the project from the Rs 20,000 crore stress fund created by Finance Minister Nirmala Sitharaman and the  funds were sanctioned for builder CCI Projects Ltd. 

  • The developer had revised the possession date to December 2019, and further extended it to June 30, 2021.

  • Home buyer had filed complaints seeking relief after the project was delayed. However, The buyer made remaining payments for the flat even after the possession date in their registered agreements had lapsed.

  • Advocate, appearing for the developer, contended that the developer had informed the revised possession dates to the buyers from time to time and they have made payments even after the possession dates had passed. This showed that they had "acquiesced" and had consented to the revised possession dates.

  • However, rejecting the argument, The Court observed that the payments were structured as slab-wise payments, and after investing big amounts, the complainants were helpless and continued making payments in the hope of early possession."Therefore, this conduct of the complainants does not amount to acquiescence. 

  • The Court Observed that “ when the statute imposes strict duty for completing the project as per timeline, and speaks about the consequences of delay, the allottees' consent for condoning the delay must be unequivocal and it must be in writing. No such document is produced before me,".

  • The Plea for granting Delayed Possession charges under Section 18 was granted.