In the matter of LAUREATE BUILDWELL PVT. LTD. V/s CHARANJEET SINGH CIVIL APPEAL NO. 7042 of 2019 decided on July 22, 2021 before THE SUPREME COURT OF INDIA
Fact of the Case
- Ms. Madhabi Venkatraman (hereafter “the original allottee”) applied on 29.08.2012 for allotment of a residential flat (No. 7013,(hereafter “the flat”) admeasuring 4545 sq. ft., in Nectarine Tower "PARX LAUREATE" at Sector- 108, Expressway, Noida.
- On 16.10.2012, an allotment letter was issued to the original allottee
- According to the allotment letter, the possession of the flat was to be handed over within 36 months (from the date of allotment letter) i.e., latest by 15.10.2015.
- The original allottee made payment to the tune of ₹1,55,89,329/
- after noticing the slow pace of construction, the original allottee decided to sell the flat
- The purchaser and now complainant alleged that possession was not delivered in October, 2015 as promised (in the allotment letter).
- The Complainant claims to have visited the builder’s office in last week of January, 2017 and was informed that possession of the said flat could not be delivered till the end of year 2017
- After this, the purchaser sought for refund of the amount paid, from the builder. On 08.03.2017, a legal notice was issued to the builder asking for refund of the amount of ₹1,93,70,883/- with interest
- The builder, Laureate denied the claim
- . It is in these circumstances, that the appellant approached the NCDRC, for direction to the builder to refund the entire sum of ₹1,93,70,883/- with interest at the rate of 24% from the respective dates when the instalments were paid to Laureate. In addition, ₹ 5,00,000/- as compensation and ₹ 2,00,000/- as litigation expenses were sought along with other costs.
- The NCDRC directed the Developer to refund the amount deposited with the developer in respect of subject flat No. 7013 with interest @ 10% p.a
- Learned senior counsel submits that since the complainant was not the original allottee but a subsequent purchaser, he could not claim any interest. He relied upon two rulings of this Court in HUDA v. Raje Ram and the recent judgment of this Court in Wing Commander Arifur Rahman Khan and Anr. v. DLF Southern Homes Pvt. Ltd.
- It is submitted that in both these cases, this Court had categorically ruled that when the allottee in a housing project transfers his or her rights in favor of another, such a third party cannot claim equities to the same extent as the original allottee, especially as regards a claim for interest
- this court is of the opinion that the per se bar to the relief of interest on refund, enunciated by the decision in Raje Ram (supra) which was applied in Wg. Commander Arifur Rehman (supra) cannot be considered good law.
- The nature and extent of relief, to which a subsequent purchaser can be entitled to, would be fact dependent.
- It would no doubt be fair to assume that the purchaser had knowledge of the delay. However, to attribute knowledge that such delay would continue indefinitely, based on an a priori assumption, would not be justified.
- the interests of justice demand that interest at least from that date ( Subsequent allottee purchasing the unit" should be granted, in favor of the respondent.