Search This Blog

Translate the Site.

Showing posts with label NCDRC Orders. Show all posts
Showing posts with label NCDRC Orders. Show all posts

Friday, 23 July 2021

Supreme Court of India - The nature and extent of relief, to which a subsequent purchaser can be entitled to, would be fact dependent.

 In the matter of LAUREATE BUILDWELL PVT. LTD. V/s CHARANJEET SINGH CIVIL APPEAL NO. 7042 of 2019 decided on July 22, 2021 before THE SUPREME COURT OF INDIA

Fact of the Case

  • Ms. Madhabi Venkatraman (hereafter “the original allottee”) applied on 29.08.2012 for allotment of a residential flat (No. 7013,(hereafter “the flat”) admeasuring 4545 sq. ft., in Nectarine Tower "PARX LAUREATE" at Sector- 108, Expressway, Noida.


  • On 16.10.2012, an allotment letter was issued to the original allottee

  • According to the allotment letter, the possession of the flat was to be handed over within 36 months (from the date of allotment letter) i.e., latest by 15.10.2015.

  • The original allottee made payment to the tune of ₹1,55,89,329/

  • after noticing the slow pace of construction, the original allottee decided to sell the flat

  • The purchaser and now complainant alleged that possession was not delivered in October, 2015 as  promised (in the allotment letter).

  • The Complainant claims to have visited the builder’s office in last week of January, 2017 and was informed that possession of the said flat could not be delivered till the end of year 2017

  • After this, the purchaser sought for refund of the amount paid, from the builder. On 08.03.2017, a legal notice was issued to the builder asking for refund of the amount of ₹1,93,70,883/- with interest

  • The builder, Laureate denied the claim

  • . It is in these circumstances, that the appellant approached the NCDRC, for direction to the builder to refund the entire sum of ₹1,93,70,883/- with interest at the rate of 24% from the respective dates when the instalments were paid to Laureate. In addition, ₹ 5,00,000/- as compensation and ₹ 2,00,000/- as litigation expenses were sought along with other costs.

  • The NCDRC directed the Developer to refund the amount deposited with the developer in respect of subject flat No. 7013 with interest @ 10% p.a

Arguments of the Builder 

  • Learned senior counsel submits that since the complainant was not the original allottee but a subsequent purchaser, he could not claim any interest. He relied upon two rulings of this Court in HUDA v. Raje Ram and the recent judgment of this Court in Wing Commander Arifur Rahman Khan and Anr. v. DLF Southern Homes Pvt. Ltd.

  • It is submitted that in both these cases, this Court had categorically ruled that when the allottee in a housing project transfers his or her rights in favor of another, such a third party cannot claim equities to the same extent as the original allottee, especially as regards a claim for interest

Analysis and Conclusions:

  • this court is of the opinion that the per se bar to the relief of interest on refund, enunciated by the decision in Raje Ram (supra) which was applied in Wg. Commander Arifur Rehman (supra) cannot be considered good law. 

  • The nature and extent of relief, to which a subsequent purchaser can be entitled to, would be fact dependent.

  • It would no doubt be fair to assume that the purchaser had knowledge of the delay. However, to attribute knowledge that such delay would continue indefinitely, based on an a priori assumption, would not be justified.

  • the interests of justice demand that interest at least from that date ( Subsequent allottee purchasing the unit" should be granted, in favor of the respondent.

Saturday, 22 May 2021

Supreme Court - Consumer disputes are non-arbitrable, in the presence of Special act like the Consumer Protection Act.

 In the Matter of M/S Emaar Mgf Land Limited vs Aftab Singh Complaint no. (2019) 12 SCC 751 decided on 10.12.2018 before Supreme Court of India


The appeals were filed challenging the order of National Consumer Disputes Redressal Commission (NCDRC) in Aftab Singh v. Emaar MGF Ltd., 2017 SCC OnLine NCDRC 1614 holding consumer disputes to be non-arbitrable.The respondent entered into a buyer’s agreement with the petitioner company for the purchase of a villa in the township to be developed by them. Dispute arose regarding the same. The respondent filed a complaint with NCDRC under Consumer Protection Act, 1986 for certain reliefs in the matter. The company relied on the arbitration clause provided in the agreement and filed an application under Section 8 of the Arbitration and Conciliation Act, 1996 for referring the matter to arbitration. This application was rejected by NCDRC. The company filed appeals against NCDRC order which was dismissed by the Delhi High Court as well as the Supreme Court.


The Hon'ble Supreme Court considered the provisions of Consumer Protection Act, 1986 & Once the public Statute is in place, Arbitration & Conciliation act 1996 can not be resorted to.It was observed that , “….complaint under Consumer Protection Act being a special remedy, despite there being an arbitration agreement the proceedings before Consumer Forum have to go on….”  Thus, it was held that the Consumer Protection Act being special legislation, NCDRC was right in rejecting the company's application under Section 8 of Arbitration Act. Therefore, the review petition was dismissed.

NCDRC - The Developer having received the sales consideration Cannot Charge Holding charges from the Allottee for the delay in taking possession.

 In the Matter of Capital Greens Flat Buyer Association & Ors. Vs. DLF Universal Limited & Anr Complaint no.Consumer case no. CC/2047/2016 decided on 03.01.2020 before National Consumer Disputes Redressal Commission


The NCDRC Observed that

36. ………………...As far as holding charges are concerned, The Developer having received the sales consideration has nothing to lose by holding possession of the allotted flat except that it would be required to maintain the apartment.Therefore the holding charges will not be payable to the developer. Even in a case where the Possession has been delayed on account of the allottee having not paid the entire sale consideration, the developer shall not be entitled to any holding charges though it would be entitled to interest for the period the payment is delayed.


in Civil Appeal CA 3864-3889/2020 Order dated 14.12.2020 the Supreme court has Upheld all directions of NCDRC except two 

(i) The compensation on account of delay in handing over possession of the flats to the flat buyers is reduced from 7% to 6%; and

(ii) The direction for the refund of parking charges and club charges and interest on these two components shall stand set aside.

NCDRC - compensation to the complainant company cannot be at par with that to an individual.The company is not entitled to compensation for the mental agony and harassment to which an individual is entitled

 In the Matter of Springdale Core Consultants Pvt Ltd vs. Pioneer Urban Land and Infrastructure Ltd Complaint no, Consumer case no. 349/2017 decided on 14.07.2020 before National Consumer Disputes Redressal Commission.


The Complainant company booked a residential apartment for its Directors in the Builders project on 29.11.2011. An agreement for sale dated 13.03.2012 was executed between the parties. Under the agreement, the Builder had to apply for Occupancy certificate by 04.09.2015 and obtain the OC by 04.03.2016. The builder could not obtain OC within agreed time. The Complainant filed a complaint seeking possession of the flat along with the compensation for delay in construction. Alternatively, the complainant company prayed for refund of the amount paid to the Builder. During the pendency of the complaint, the Builder obtained OC and offered possession to the complainant company vide letter dated 03.04.2019. 


Issue before NCDRC: 

(i) Whether the flat booked by the Complainant company for its Directors was booked for speculative purposes? 

(ii) Whether the Complainant company is entitled to any compensation in the form of interest for delay in possession of flat?

It placed reliance on the resolution passed by its board of directors on 14.11.2011, resolving to book flat for the residence of one of the directors of the company. Accordingly, the complainant argued that the purchase of flat was not for speculative purposes. 


Builder’s contentions: 

1. Since the complainant is a private limited company resolution may have been manufactured at a later date. 2. As per the information provided by the Registrar of companies, the business activities of the complainant company were confined to Amritsar and all the Directors were residents of Amritsar. A director was also a partner of LLP engaged in the business of Real estate. 

3. The compensation for the delay in delivery of the possession where the complainant is a company should not be at par with the compensation granted to an individual. 

4. Submitting the lease deeds, the builder showed the prevailing rentals in the project. They stated that there would be no justification for compensation higher than the prevailing rentals in the project.

5. Builder also claimed for holding charges from the complainant company.


Verdict of NCDRC: 

NCDRC directed the Builder to hand over the possession of flat to the complainant company within 8 weeks from the date of order. The court also awarded compensation to the complainant company. It rejected the Builder’s contention that the flat in question was for speculative purposes. It observed that the Director became a partner in the LLP in the year 2017 and the flat in question was booked earlier in the year 2011. Secondly, she was residing at Gurgaon and was planning to shift to Gurgaon even if she was residing at Amritsar. Therefore, it is difficult to infer that the flat was booked for speculative purposes 


The Commission relied on the decision of Vishal Malik & Anr. Vs. Pioneer Urban Land Infrastructure Ltd 1 , to direct possession of flat along with the compensation. The commission agreed with the Builder that the compensation to the complainant company cannot be at par with that to an individual. 

The company is not entitled to compensation for the mental agony and harassment to which an individual is entitled. On quantum of compensation, NCDRC stated that the prevailing rents in respect of similarly situated flats of identical specifications and size cannot be made the sole basis for grant of such compensation. Else the builder would have no incentive to complete the construction within the agreed time frame. He would know that even if he diverts the funds collected from the flat buyer to another project, he would easily compensate the buyer which would not cost him more than 3-4% of the capital employed. 


NCDRC placed reliance on the decision of Capital Greens Flat Buyer Association & Ors. Vs. DLF Universal Limited & Anr 2 to observe that the builder is not entitled to holding charges. Since the builder having received the consideration has nothing to lose by holding possession of flat except to maintain the apartment.

Friday, 21 May 2021

NCDRC - Wherever the builder commits a particular date or time frame for completion of the construction and offering possession to the buyer, he must necessarily honour the commitment made by him, If the builder can indefinitely postpone and delay the construction of the flat and the flat buyer has no option but to wait till the builder decides to complete the construction and offer possession to the buyer, that would be nothing but a travesty of justice.

 In the Matter of Pradeep Narula & Anr. Vs. M/s. Granite Gate Properties Pvt. Ltd. & Anr. Complaint no. Consumer Case No. 315 OF 2014 decided on 23.08.2016 before National Consumer Disputes Redressal Commission


The NCDRC in this case Observed that 


"10.   ...........  The primary purpose of a consumer in booking a residential flat which the builder is to construct for him, is to start living in that house on or about the date committed to him by the builder for delivering possession of the flat booked by him.  If the builder does not deliver upon his contractual obligation and at the same time, is unable to show that the delay in completion of the flat and offering its possession to the consumer was on account on circumstances beyond his control, this would constitute deficiency on the part of the builder / service provider in rendering services to the consumer.  If I accept the contention that the builder can indefinitely postpone and delay the construction of the flat and the flat buyer has no option but to wait till the builder decides to complete the construction and offer possession to the buyer, that would be nothing but a travesty of justice and result in a situation where the flat buyer is left at the mercy of the builder, without recourse to an appropriate legal remedy.  Such an interpretation, if taken, is bound to defeat the very objective behind the enactment of the Consumer Protection Act, as far as housing construction is concerned.  Therefore, I am unable to accept the contention advanced by the learned counsel for the opposite party.  In my view, wherever the builder commits a particular date or time frame for completion of the construction and offering possession to the buyer, he must necessarily honour the commitment made by him, though a minor delay may not constitute deficiency in the service rendered by him to the buyer.  Of course, if the builder is able to how that the delay in completion of the construction and offering possession to the buyer is attributable wholly to the circumstances beyond his control, that may not be a case of deficiency in the services rendered to the consumer".

NCDRC - The builder ought not to have accepted money and entered into agreement with the buyers without approval of the building plans

 In the Matter of Yogesh Sharma & Anr., vs M/S Unitech Limited Complaint no.Consumer Case No. 267 OF 2014  decided on 26.11.2015 before National Consumer Disputes Redressal Commission


The NCDRC in the case observed that the builder ought not to have accepted money and entered into agreement with the buyers without approval of the building plans by GNIDA (Greater Noida Development Authority). If the opposite party chose to accept money from the flat buyers and enter into agreements, undertaking to give possession within a particular time frame, without having possession of the land and without approval of the building plans, it is only itself to blame for a situation in which the construction got delayed on account of the delay in approval of building plans and physical delivery of the land to it on the spot.

Tuesday, 13 April 2021

SUPREME COURT in Consumer Protection Act: Flat buyers are entitled to just reasonable compensation on gross delay & execution of the Deed of Conveyance by a flat purchaser Does not precludes a consumer claim being raised for delayed possession

 IN THE MATTER OF: 

Wg. Cdr. Arifur Rahman Khan and Aleys Sultana and Ors. Vs. DLF Southern Homes Pvt. Ltd. (now known as BEGUR OMR Homes Pvt. Ltd.) & Ors. (Decided by Hon’ble Supreme Court of India on 24.08.2020)

Issues: 

Issue 1.Whether the flat buyers are entitled to compensation in excess of what was stipulated in the Apartment Buyers Agreement?

Issue 2.Whether the execution of the Deed of Conveyance by a flat purchaser precludes a consumer claim being raised for delayed possession?

Facts: 

1.The Complaint before the National Consumer Disputes Redressal Commission (NCDRC) was initially instituted by nine flat buyers. These Complainants had booked residential flats in a project called Westend Heights at New Town, DLF, BTM Extension at Begu, Bengaluru. The brochure of the first respondent advertised the nature of the project and the amenities which would be provided to buyers. Responding to the representation held out by the developer, the complainants booked flats in the residential project. The flat buyers entered into agreements with the developer. Clause 11(a) of the Apartment Buyer’s Agreement (ABA) indicated that the developer would endeavor to complete construction within a period of thirty-six months from the date of the execution of the agreement save and except for force majeure conditions. The developers issued various communications indicating the progress of the work and kept on changing the timeline of delivery of possession. Further, there was an admission of the fact that until 2015, the occupation certificate had not been received. Thus, the obligation to handover possession within a period of thirty-six months was not fulfilled.

2.The first batch of nine flat purchasers moved a consumer complaint before the NCDRC complaining of a breach by the developer of the obligation, contractually assumed, under the terms of the ABA. Since the nine complainants purported to represent the entire group of flat purchasers, a notice of the complaint under Section 12(1)(c) of the Consumer Protection Act 19863 was published in the newspapers. An I.A. was filed before the NCDRC under Section 12(1)(c) which was subsequently disposed of by NCDRC, which led to an appeal before the Apex Court. Procedural directions issued upon several impleadment applications resulted in a further order of the Apex Court reiterating that the complaint would be treated as having been filed on behalf of 339 persons. By the aforesaid order, the Apex Court had laid down a peremptory time schedule of six months for the disposal of the complaint.

3.The NCDRC divided the group of 339 flat buyers into six groups based on whether or not they had taken possession, executed deeds of conveyance, settled the dispute or sold the flats before or during the pendency of the complaint or their applications for impleadment. While recording a finding of fact that there was an admitted delay on the part of the developer, the NCDRC held that the agreements provided compensation at the rate of Rs.5/- per square foot of the super area for every month of delay. The NCDRC held that the flat purchasers who agreed to this stipulation in the agreements were not entitled to seek any amount in addition. Further, the execution of the Deed of Conveyance by a flat purchaser would preclude a consumer claim being raised for delayed possession.

4.The NCDRC dismissed the consumer complaint filed by 339 flat buyers, accepting the defense of DLF Southern Homes Pvt. Ltd. and Annabel Builders and Developers Pvt. Ltd. that there was no deficiency of service on their part in complying with their contractual obligations and, that despite a delay in handing over the possession ofthe residential flats, the purchasers were not entitled to compensation in excess of what was stipulated in the Apartment Buyers Agreement (ABA). Aggrieved by the order of the NCDRC, the Appellants have approached the Hon’ble Supreme Court.

Supreme Court’s Observations:

 ❑ The Counsel for Appellants submitted that – 

     i) There is a gross delay ranging between two and four years in handing over possession and the flat buyers ought not to be constrained by the terms of the agreement which are one-sided and unreasonable; 

(ii) The execution of conveyances or settlement deeds would not operate to preclude the flat buyers from claiming compensation; and 

(iii) The amenities which have been contracted for have not been provided by the developers. Pursuant to the aforesaid, the Counsel for Respondents submitted that –         i) No evidence has been led by the complainants to discharge the onus placed upon them to establish coercion or duress while executing conveyances or settlements; 

            (ii) Possession of the complex, comprising of 813 apartments in nineteen towers has been handed over between four to six years ago and the developer has transferred his right, title and interest to the Residents‟ Welfare Association (“RWA”); 

            (iii) Out of 171 applicants, 145 have received compensation at the agreed rate while handing over possession; and (iv) Under clause 14 of the ABA, the flat buyers have been compensated at the rate of Rs 5 per square foot per month. No proof or measure of actual loss suffered has been adduced. 

❑ The Court observed that the developer has accepted that there was a delay on his part which triggered of the liability to pay compensation. A failure of the developer to comply with the contractual obligation to provide the flat to a flat purchaser within a contractually stipulated period amounts to a deficiency. There is a fault, shortcoming or inadequacy in the nature and manner of performance which has been undertaken to be performed in pursuance of the contract in relation to the service. Under Section 14(1)(e), the jurisdiction of the consumer forum extends to directing the opposite party inter alia to remove the deficiency in the service in question. 

Further, in assessing the legal position, it is necessary to record that the ABA is clearly one-sided. Evidently, the terms of the agreement have been drafted by the Developer. They do not maintain a level platform as between the developer and purchaser. The stringency of the terms which bind the purchaser are not mirrored by the obligations for meeting times lines by the developer. The agreement does not reflect an even bargain. Where, as in the present case, there has been a gross delay in the handing over of possession beyond the contractually stipulated debt, the Court is clear of the view that the jurisdiction of the consumer forum to award just and reasonable compensation as an incident of its power to direct the removal of a deficiency in service is not constrained by the terms of a rate which is prescribed in an unfair bargain. 

❑ The Court further observed that the flat purchasers have invested their hard earned money. It is only reasonable to presume that the next logical step is for the purchaser to perfect the title to the premises which have been allotted under the terms of the ABA. But the submission of the developer is that the purchaser forsakes the remedy before the consumer forum by seeking a Deed of Conveyance. To accept such a construction would lead to an absurd consequence of requiring the purchaser either to abandon a just claim as a condition for obtaining the conveyance or to indefinitely delay the execution of the Deed of Conveyance pending protracted consumer litigation. 

Thus, disapproving the view of NCDRC, the Apex Court held that flat purchasers who obtained possession or executed Deeds of Conveyance have not lost their right to make a claim for compensation for the delayed handing over of the flats. After making the aforesaid observations, the Court has directed that - 

        i) Except for eleven appellants who entered into specific settlements with the developer and three appellants who have sold their right, title and interest under the ABA, the respondents shall, as a measure of compensation, pay an amount calculated at the rate of 6 per cent simple interest per annum to each of the appellants. The amount shall be computed on the total amounts paid towards the purchase of the respective flats with effect from the date of expiry of thirty-six months from the execution of the respective ABAs until the date of the offer of possession after the receipt of the occupation certificate; 

         ii) The above amount shall be in addition to the amounts which have been paid over or credited by the developer at the rate of Rs 5 per square foot per month at the time of the drawing of final accounts; and 

          iii) The amounts due and payable in terms of directions (i) and (ii) above shall be paid over within a period of one month from the date of this judgment failing which they shall carry interest at the rate of 9% p.a. until payment.


Thursday, 1 April 2021

Only a reasonable amount can be forfeited as earnest money.

 In the Matter of DLF Ltd. v. Bhagwanti Narula, I (2015) CPJ 319(NC) the Hon’ble National Consumer Disputes Redressal Commission has clearly laid down that only a reasonable amount can be forfeited as earnest money in the event of default on the part of the purchaser and it is not permissible in law to forfeit any amount beyond a reasonable amount unless it is shown that the person forfeiting the said amount had actually suffered loss to the extent of the amount forfeited by him. Further, it was held that 20 % of the sale price cannot be said to be a reasonable amount which the petitioner company could have forfeited on account of default on the part of the complainant unless it can show it had suffered loss to the extent the amount was forfeited by it.


Escalation Cost in the Event of Delayed Possession are to be borne by the builder only

In the Matter of  Brig. (Retd.) Kamal Sood V/s DLF Universal Ltd.(FA /557 /2003)  Date of Order 02.04.2007 The NCDRC observed that

         “it was the duty of the builder to plan in advance, obtain necessary permission and thereafter, promise to deliver the possession of flat in the stipulated time. It is unfair trade practice on the part of the builder to collect money from the prospective buyers without obtaining the required permission.Secondly, in such a case, if there is any express promise that the premises would be delivered within the stipulated time, and, if not done so, escalation cost is required to be borne by the builder.”