Search This Blog

Translate the Site to your native language

Showing posts with label Section 14(2) of RERA Act. Show all posts
Showing posts with label Section 14(2) of RERA Act. Show all posts

Tuesday, 22 September 2026

Telangana REAT Upholds ₹27.50 Lakh Penalty Against Promoter for Additional Clubhouse Floor and Revised Plan Without Allottees’ Consent

Telangana REAT Upholds ₹27.50 Lakh Penalty Against Promoter for Additional Clubhouse Floor and Revised Plan Without Allottees’ Consent

Case: Trendset Jayabheri Projects LLP & Ors. v. Neelima Vanguru
Case No.: T.A. No. 35 of 2024
Forum: Telangana Real Estate Appellate Tribunal (TSREAT)
Citation: 2026 LLBiz REAT (TS) 69

The Telangana REAT dismissed the promoter’s appeal and upheld the ₹27.50 lakh penalty imposed by TG RERA in relation to an additional floor constructed in the project’s clubhouse/amenities block. 

Background

The dispute concerned the Trendset Jayabheri Elevate project at Kondapur, Hyderabad. The project is registered with Telangana RERA as P02400000452. 

The allottee, Neelima Vanguru, alleged that the promoter had:

  • obtained a revised sanctioned plan without obtaining the requisite consent of the allottees;

  • failed to upload/disclose the revised plan to the allottees as required under RERA; and

  • constructed an additional floor in the clubhouse/amenities block.

Findings of Telangana REAT

The Tribunal noted that the original building permission showed the amenities block as Ground + 2 floors. Subsequently, another building permit dated 25 May 2023 reflected the amenities block as Ground + 3 upper floors.

The Tribunal found that the promoter had not uploaded the revised sanctioned plan, amounting to a violation of Section 11(3) of the RERA Act, which requires the promoter to make relevant sanctioned plans and revisions available to allottees.

More importantly, the Tribunal held that the promoter had not obtained the consent of two-thirds of the allottees before obtaining the revised sanctioned plan, thereby violating Section 14(2) of RERA. 

Section 14(2) — significance

Section 14(2) restricts a promoter from making alterations or additions in the sanctioned plans and specifications except in accordance with the statutory requirements, including obtaining the consent of at least two-thirds of the allottees for material alterations/additions.

The Tribunal therefore rejected the promoter's contention that the additional clubhouse floor was merely a minor deviation which benefited allottees and did not impose any additional financial burden upon them. 

Section 11(4)(f) and common areas

The Tribunal also relied upon Section 11(4)(f) read with Section 17, observing that the promoter was required to convey the undivided proportionate title in the common areas to the association of allottees.

The clubhouse, including the additional floor, formed part of the common amenities/common areas. Consequently, the promoter could not treat the alteration as inconsequential merely because it did not result in an additional charge to the allottees. 

Final decision

The Telangana REAT dismissed the appeal and upheld the ₹27.50 lakh penalty imposed by TG RERA. It found the RERA order to be legally sustainable and based on appreciation of the facts and applicable provisions of RERA.

Key RERA proposition

A promoter cannot avoid the requirement of obtaining the requisite consent under Section 14(2) merely by characterising a deviation in the sanctioned plan as minor or beneficial to the allottees. Failure to disclose the revised sanctioned plan may independently constitute a violation of Section 11(3).

This case is particularly useful when dealing with unauthorised/revised building plans, alterations in common amenities, clubhouse modifications, and the requirement of two-thirds allottees' consent under Section 14(2) of RERA. (Live Law 

Sunday, 20 September 2026

2/3rd Allottee Consent Under Section 14(2) of RERA Required Only for Alterations Beyond the Development Agreed Under the Agreement for Sale: K-RERA”

 

2/3rd Allottee Consent Under Section 14(2) of RERA Required Only for Alterations Beyond the Development Agreed Under the Agreement for Sale: K-RERA

Raintree Boulevard Apartment Owners Association v. L&T Realty Developers Limited

Case: Raintree Boulevard Apartment Owners Association v. L&T Realty Developers Limited
Forum: Karnataka Real Estate Regulatory Authority (K-RERA)
Complaint No.: 00772/2025

The matter concerned a complaint by the Raintree Boulevard Apartment Owners Association against L&T Realty Developers Limited in relation to alleged unauthorised modifications and commercial development associated with the project. The Association sought, inter alia, revocation of the promoter's project registration and demolition of the commercial buildings.

Key finding

K-RERA held that the requirement of obtaining the consent of two-thirds of the allottees under Section 14(2) of the RERA Act is attracted only where the proposed alteration is beyond what was mutually agreed between the promoter and the allottees under the agreement/sale documents.

In other words, not every change or alteration in a real estate project automatically requires consent of two-thirds of the allottees. The first question is whether the proposed change goes beyond the development that was contractually agreed with the allottees.

K-RERA relied upon an earlier appellate tribunal ruling in reaching this conclusion. The Authority consequently dismissed the Association's complaint seeking revocation of registration and demolition.

Legal proposition

The decision can be usefully stated as:

The statutory requirement of consent of two-thirds of the allottees is triggered when the promoter proposes an alteration which goes beyond what was mutually agreed under the agreement for sale; the mere existence of an alteration does not, by itself, attract Section 14(2).

Relevance under RERA

The ruling is particularly relevant when dealing with allegations concerning:

  1. change in sanctioned plans;
  2. alteration/addition to the project;
  3. development of commercial components;
  4. demolition/removal of structures;
  5. whether 2/3rd allottee consent is mandatory; and
  6. the scope of Section 14(2) of the RERA Act.

The decision also illustrates the importance of examining the agreement for sale and the original contractual representation regarding the project, rather than treating every subsequent modification as requiring statutory consent.

Friday, 18 September 2026

Maharashtra REAT Imposes Penalty Equivalent to 2% of Project Cost on RA Associates for Altering Project Plan Without Allottees’ Consent

Maharashtra REAT Imposes Penalty Equivalent to 2% of Project Cost on RA Associates for Altering Project Plan Without Allottees’ Consent

Case Title: RA Residences Co-operative Housing Society Ltd. v. RA Associates & Ors.
Case No.: Appeal No. AT06/00804/2025
Date of Decision: 16 September 2026
Forum: Maharashtra Real Estate Appellate Tribunal (MahaREAT)

The Maharashtra Real Estate Appellate Tribunal (MahaREAT), by its judgment dated 16 September 2026, imposed a penalty equivalent to 2% of the project cost upon RA Associates and its partners, the promoters of the “RA Residences” project in Mumbai, for altering the disclosed project plans and increasing the Floor Space Index (FSI) of the commercial building without obtaining the requisite prior consent of the allottees.

A Bench comprising Chairperson Justice S.S. Shinde and Administrative Member Shrikant M. Deshpande further directed the promoters to execute the conveyance of the residential building within 60 days. The Tribunal held that a promoter cannot indefinitely defer conveyance on the ground that additional FSI or Transferable Development Rights (TDR) may become available in the future.

The Tribunal observed:

“...In fact, once the FSI available in the project property is exhausted, the promoters are obligated to execute the conveyance and are not entitled to any further FSI, if available, due to change in policy within the property or procured from elsewhere.”

Background

The dispute arose in relation to the “RA Residences” project in Mumbai, comprising residential Wings A and B and a separate commercial/IT building. The promoters had initially proposed to complete the project by 30 June 2018, following which the registration of the project was extended by the Maharashtra Real Estate Regulatory Authority (MahaRERA).

Part occupation certificates for the residential wings were obtained on 23 June 2020, 15 December 2020 and 9 December 2021, while the housing society was registered on 18 October 2022.

The society subsequently approached MahaRERA alleging, inter alia, that the promoters had:

  • materially altered the sanctioned and disclosed plans;

  • utilised additional FSI without obtaining the requisite consent of the allottees;

  • altered common and recreational areas;

  • failed to execute the conveyance; and

  • failed to hand over project documents, amenities and other facilities.

MahaRERA, by its order dated 7 July 2025, partly allowed the complaint and held that the promoters had violated Section 14(2) of the Real Estate (Regulation and Development) Act, 2016, which requires the prior consent of at least two-thirds of the allottees for specified alterations or additions to sanctioned plans.

The society thereafter preferred an appeal before MahaREAT seeking further reliefs.

Alteration of Plans Without Consent

Before the Tribunal, the promoters contended that the residential buildings had been completed in accordance with the sanctioned plans and that occupation certificates had been obtained. They further relied upon the agreements for sale, contending that the contractual arrangements contemplated separate residential and commercial structures and permitted development through additional FSI/TDR.

The Tribunal, however, held that the promoters had violated Section 14 of RERA by altering the disclosed sanctioned plans without obtaining the requisite consent of the allottees.

The Tribunal also found violations of Section 11 of RERA, which prescribes the promoter's statutory obligations, including obligations concerning conveyance.

Consent Under RERA and MOFA Cannot Be Contractually Dispensed With

The Tribunal additionally held that the promoters had violated Section 7 of the Maharashtra Ownership Flats Act (MOFA), which requires the consent of flat purchasers for additions or alterations to the structure disclosed to them.

In particular, the Tribunal noted that construction of the commercial C-Wing under the revised 2021 plan required the consent of two-thirds of the allottees.

Significantly, it rejected the promoters' reliance upon deemed-consent clauses contained in the agreements for sale, observing:

“the deemed consent in the clauses of the agreements for sale is not the consent within the meaning of consent under section 7 of MOFA or section 14 of RERA.”

Thus, contractual provisions cannot be treated as a substitute for the statutory consent contemplated under RERA and MOFA.

Additional FSI/TDR and Entitlement of the Societies

The Tribunal further held that the additional FSI/TDR utilised by the promoters, but not disclosed in the 2017 plan, belonged to the societies representing the residential and commercial buildings of the project.

The Tribunal therefore directed proportionate apportionment of the sale proceeds generated from commercial units constructed by utilising the additional 4,225.57 square metres of FSI.

The finding assumes significance in the context of the promoter's rights over additional development potential after the disclosure of the original project plans and the rights of the allottees/societies in such additional development potential.

Conveyance Cannot Be Deferred Indefinitely

Since Wings A and B had received occupation certificates and possession had been handed over to the respective allottees, the Tribunal directed the promoters to complete the conveyance of the residential building.

It specifically rejected the proposition that conveyance could be postponed merely because additional FSI or TDR might become available in the future. The Tribunal held that once the FSI available in the project property has been exhausted, the promoters are required to execute the conveyance and cannot retain rights over future FSI merely because of a subsequent change in policy or because additional FSI/TDR may be procured from another source.

Accordingly, the promoters were directed to convey the residential building's proportionate interest in the project property, together with the relevant common areas and amenities, within 60 days.

Maintenance, Clubhouse and Corpus Fund

The Tribunal also considered amounts collected by the promoters towards maintenance charges, clubhouse charges and corpus fund.

Since the residential buildings had been completed and possession had been handed over, MahaREAT directed the promoters to furnish audited accounts of the amounts collected under these heads.

The Tribunal observed:

“Since the residential building (wing 'A' and wing 'B') is completed with occupation certificate and the allottees have taken the possession of their respective flats, we deem it appropriate to direct the promoters to provide audited accounts of the amounts collected under agreements towards maintenance charges, clubhouse charges, and corpus fund and refund the amount as per the audited accounts to the appellant with accrued interest on the said amount, if kept in a separate account.”

The promoters were consequently directed to refund the balance amount to the society, along with accrued interest wherever applicable.

Other Directions

MahaREAT further directed the promoters to:

  1. hand over the remaining 64 guest parking spaces;

  2. execute the conveyance of the residential building's proportionate interest in the project property;

  3. hand over the relevant common areas and amenities;

  4. furnish audited accounts concerning maintenance, clubhouse and corpus-fund collections; and

  5. refund the balance amounts to the society with applicable interest.

The issues relating to incomplete works, repairs, deficiencies in services and rectification of defects were remanded to MahaRERA for fresh adjudication.

Key Takeaway

The decision reiterates that the promoter's contractual rights under an agreement for sale do not override the statutory protections afforded to allottees under RERA and MOFA. Alterations to disclosed plans and structures requiring statutory consent cannot be justified merely by relying upon deemed-consent clauses in agreements for sale.

The ruling also emphasises that future availability of FSI/TDR cannot be used as an indefinite ground to postpone conveyance once the relevant project development has reached the stage where conveyance is required. Further, where additional development potential is utilised in a manner not disclosed in the original project plan, the Tribunal may examine the consequential rights of the societies/allottees in the benefits arising from such additional development.

Sunday, 16 May 2021

Complainant is stopped from denying/withdrawing his consent given for the re-planning of the building ,the Complainant's claim for withdrawal after accepting the offer is not maintainable.

 In The Matter of Sunil Wadhwani v. Pashmina Realty Private Limited Complaint number CC006000000078745 Decided on 07.01.2020 before Maharashtra Real Estate Regulatory Authority

  • The Complainant had booked flat no. C-701 having carpet area of 1,436 square feet consisting of 4 (four) bedrooms in the Respondent's project 'Pashmina Lotus' situated at Chandivali, Powai ("the Original Flat"), at and for a consideration of Rs. 2,76,00,000/-.

  • The Respondent agreed to handover possession of the Original Flat by 30th September, 2016. However, the project was not viable, the plans were revised and two bedroom and three-bedroom flats were proposed to be constructed with the consent of 2/3rd (two-third) allottees of the project including the Complainant. 

  • A new development manager was brought in and the development was rebranded and re-registered under RERA under a new name.

  • The Complainant gave express consent for the change in plan on 27th December, 2017 in the form of consent terms ("Consent Letter") whereby the Complainant has given consent to two flats being flat no. B-1104 admeasuring 770 square feet carpet area and flat no. A-1101 admeasuring 812 square feet carpet area ("New Flats") and gave consent for re-planning the building under Section 14(2) of RERA.

  • After the Consent, the Complainant sought refund of his amount with interest under Section 18 of the RERA claiming that the Respondent failed to hand over the possession of the Original Flat on the agreed date.


Issue:

  • Whether the Complainant is stopped from denying/withdrawing his consent given for the re-planning of the building?


Observations of Maha-RERA:


  • The consent under Section 14(2) of RERA of 2/3rd (two-third) allottees for re-planning has been given to the Respondent and the Respondent has revised the plans. The Respondent is ready to execute the agreements of the flats revised by them i.e. New Flats. Not only that, in terms of the Consent Letter, the Complainant has given his consent to accept the New Flats each consisting of two bedrooms in lieu of the Original Flat consisting of four bedrooms. The Complainant also showed his readiness to pay Rs. 20,00,000/- for additional carpet area which he is going to obtain. These facts, therefore, establish that on the consent of the Complainant, the Respondent has acted to its dis-advantage and hence, the Complainant is estopped under Section 115 of the Evidence Act from withdrawing his consent and his status as an allottee of the New Flats.


  • In context of the aforesaid, Maha-RERA observed that provisions of Section 62 of the Contract Act can also be pressed into service, which Section 62 reads as follows:

"62. If the parties to a contract agree to substitute a new contract for it, or to rescind or alter it, the original contract need not be performed."


  • Maha-RERA also relied upon the observation made by the Hon'ble Supreme Court in the context of Section 62 of the Contract Act in Lata Construction and Others v. Dr. Rameshchandra Ramniklal Shah (2001)1 SCC 586 whereby it was observed:

"Section 62 of the Contract Act contains the principle of "Novation" of contract. One of the essential requirements of "Novation", as contemplated by Section 62, is that there should be complete substitution of a new contract in place of the old. It is in that situation that the original contract need not be performed. Substitution of a new contract in place of the old contract which would have the effect of rescinding or completely altering the terms of the original contract, has to be by agreement between the parties. A substituted contract should rescind or alter or extinguish the previous contract. But if the terms of the two contracts are inconsistent and they cannot stand together, the subsequent contract cannot be in substitution of the earlier contract."


Order of the Maha-RERA:


After considering the facts and circumstances of the case, Maha-RERA found that there is novation of the contract and only a formal contract in writing is to be executed. The consideration of the Original Flat is to be adjusted against the New Flats, otherwise the terms and conditions are similar. In view of the same, the Complainant's claim for withdrawal is not maintainable and the same is dismissed.


Maha-RERA, in order to avoid multiplicity of the proceedings, in the capacity of the regulator, directed the parties to enter and register the agreement for sale of New Flats in consonance with terms and the conditions of the Consent Letter and the Previous Agreement within period of 1 (one) month.