Tuesday, 2 April 2024

NCLAT - Creditors of a class for amended Section 7(1) threshold of 10% or 100 whichever is Lower must be from a particular project registered with RERA

Pankaj Mehta V/s M/s. Ansal Hi-tech Township Limited 

Company Appeal (AT) (INS) No. 248 of 2023 

(Arising out of the `Impugned Order’ dated 06.01.2023 in CP (IB) No. 596 (PB) / 2021)

NATIONAL COMPANY LAW APPELLATE TRIBUNAL PRINCIPAL BENCH, NEW DELHI  


Time line of the Matter :-

  1. The ‘Appellant / Financial Creditor / Applicant’, along with106 other ‘Financial Creditors / Applicants’, had preferred petition ,under Section 7 of the I & B Code, 2016 before NCLT PB New Delhi.
  2.  Wherein, M/s. Ansal Hi-Tech Township Limited, was described as the ‘Corporate Debtor’ and the Total Amount of Debt, was mentioned as Rs.41,81,90,116/- 
  3. On Date 06/01/2023, NCLT,  dismissed the main Company Petition as `Not Maintainable’ terming that the `Allottees’, belong to different Sub Projects.

Fact of the Case:- 

  1. A Project by the name of  'Sushant Megapolis near Dadri Town, adjoining Greater Noida, Uttar Pradesh.  by Corporate Debtor M/s Ansal comprises of Plots / Built-up PlotsRow Houses/ Flats / Floors /  Villas / High-rise Apartments, under various allocated Sites.
  2. License for developing the Township, was granted  in Year2006, by the UP Government with the instruction of Entire Construction be completed by year 2016.
  3. By 2016 the Project was incomplete and M/s Ansal registered 25 separate projects having separate `RERA Registrations’ in this Township with RERA.
  4.  Appellants are 107 different Allottee  who purchased different types of Units such as Plots / Flats/ Apartments /EWS unit , in the Project.
  5. The Possession date of all the allottees  was from 36 months to 42 months, from the date of sanction of the `Layout Plan’ of the `Allotted Unit’. 

Submissions by Appellant

  1.  All the Applicants had entered into respective BBAs, much before the RERA Act,2016 came into force.
  2.  The said `Agreements’, specifically, defines that `Sushant Megapolis’, as one complete `Project’.
  3. The `Single Layout Plan of this project reflects Group Housing/ Plots and EWS Units as part of `One Project’, comprising of 2504 Acres of Property.
  4. A Single  Application for Environmental Clearance, was filed for the entire project. 
  5.  The Project in question, is a `Single Real Estate Project’, for the purposes of Section 7 of the IB Code, 2016.
  6. It therefore, falls under the requisite ambit of the provisos of the amended Section 7(1) of the IB Code 2016 pertaining to the minimum threshold requirement of 100 Allottees or 10% of the Total Allottees, whichever is less, belonging to the `same Real Estate project’. 
  7. The NCLT, Passed the impugned Judgment without considering the decision of Hon’ble Supreme Court in Manish Kumar v. Union of India & Ors  (2021) 5 SCC OnLine SCC 1, wherein, it is observed that a Real estate project can be a composite one for Plots and Apartments or for Plots & Buildings.
  8. Further, the definition of `Allottee’, is split into broadly three Categories Plot, Apartment and Building and the `Purchasers’ of all these are covered under the term `Allottee’ 
  9.  The interpretation, laid down by the was incorrect  that 100 or 10% of the `Allottees’, must be from the `same Building’, and `not from the same `Real Estate Project’.

Submissions by Respondent

  1. The Township, consists of Multiple Residential  and Commercial Real Estate Project, and all the sub-projects, are independent of each other and are being developed and sold as separate Projects.
  2. Each and Every phase, is registered as a stand-alone Real Estate Project under RERA with separate `RERA Registration Numbers’
  3. As per Hon’ble Supreme Court of India, that the task of ascertaining who will be Allottees and therefore, what would constitute 10% of total number of Allottees must depend upon the nature of the `Real Estate Project’.
  4.  The Petitioners do not satisfy the required threshold limit of 10% or 100 persons’, whichever is lower, in none of the Project / Project categories, 
  5. Approximately 50 Petitioners are either Co-Applicants or Third Applicants for a Single Unit just to fulfill the requisite number of 100 Allottees. whereas in the matter of Manish Kumar v. Union of India, wherein, it is held that `one unit equals to one Allottees’, even though, the said Unit is jointly held. 
  6. The NCLT  made ‘inquiry’ and considered all the records pertaining to the Project.

Observations made by the Hon’ble Court.

  1. The Corporate Debtor, had executed, at least Three different kinds of Agreements, namely  (a) `Plot Allottee Agreement’ (b) `Built-up Unit Allottee Agreement’ and (c) `Apartment Allottee Agreement as the projects were of `different character’ with `different type of developments with independent, RERA Registrations. ’
  2. In none of the Projects / Project Categories, the Applicants  fulfil the requirement of Threshold Limit’ of 10% or 100 persons, whichever is less. 
  3. the Appellant are from different numerous projects, and they have not established their case, as `Creditors of a class’, concerning any `particular project’, registered with RERA, with a view to fulfil the requirement of  Section 7 (1) of the IBC in regards to 10% or 100 Allottees’
  4. In the present case on hand, the foremost aspect to be taken into account is the RERA Registration of the Projects, of the Corporate Debtor, for ensuring the Initial limit for pressing into service of the ingredients of Section 7 of the Code. 
  5. The `Impugned Order’ and the views expressed in dismissing the CP (IB) No. 596 (PB) / 2021, is free from any `legal flaws’. 

Court’s Order

Accordingly the instant `Appeal’ sans merits is `Dismissed’ with no costs.


Friday, 11 February 2022

Supreme Court : Even after a petition under Section 7 of the IBC is admitted and before the Committee of Creditors is formed, the parties can settle the dispute

 Supreme Court : Swiss Ribbons Pvt Ltd and Anr. v. Union of India and Ors (2019) 4 SCC 17

Even after a petition under Section 7 of the IBC is admitted and before the Committee of Creditors is formed, the parties can settle the dispute. Further, even after the CoC is formed, Section 12A of the IBC does provide for a mechanism through which the petition can be withdrawn (if the parties were to reach a settlement);

Supreme Court : NCLT can not dismiss the petition on the basis that the corporate debtor has initiated the process of settlement with the financial creditors

 Supreme Court :ES Krishnamurthy v. M/S Bharath Hi Tech Builders Pvt Ltd.,

the legal issue before the apex court was whether the NCLT can, without applying its mind to the merits of the petition under Section 7, simply dismiss the petition on the basis that the corporate debtor has initiated the process of settlement with the financial creditors.

The Court found that the NCLT and NCLAT had abdicated their jurisdiction to decide a petition under Section 7 by directing the respondent to settle the remaining claims within three months, noting that such a course of action is not contemplated under the IBC except either admit or reject an application respectively contemplating occurrence of debt and default.

The Bench stated that while settlements can be encouraged by the NCLT and NCLAT to achieve the objectives of the IBC, however, "they cannot direct them by acting as courts of equity."