Search This Blog

Translate the Site to your native language

Showing posts with label cancellation. Show all posts
Showing posts with label cancellation. Show all posts

Friday, 18 September 2026

IBC Prevails Over RERA On Individual Refund Rights In CIRP; Homebuyers Bound By Class Decision On Resolution Plan: NCLT Mumbai

 

IBC Prevails Over RERA in Case of Conflict with Individual Refund Rights; Homebuyers Bound by Collective Class Decision: NCLT Mumbai

Cause Title: Vivek Talwar & Others v. Rajesh Jhunjhunwala, Resolution Professional & Others
Case No.: I.A. (IB) No. 3688 of 2025 in C.P. (IB) No. 389/MB/2022

The National Company Law Tribunal, Mumbai Bench, has held that a resolution plan cannot be required to incorporate an individual homebuyer's right to seek refund under Section 18 of the Real Estate (Regulation and Development) Act, 2016 (“RERA”), where enforcement of such individual right is inconsistent with the collective insolvency resolution process contemplated under the Insolvency and Bankruptcy Code, 2016 (“IBC”).

A Bench comprising K.R. Saji Kumar, Member (Judicial), and Anil Raj Chellan, Member (Technical), dismissed an application filed by four homebuyers seeking reconsideration of the resolution plan of Spenta Enclave Private Limited and, alternatively, seeking directions for provision of an exit and refund mechanism for homebuyers who did not wish to continue with their respective units.

The applicants had booked two flats in the “Altavista” project developed by Spenta Enclave Private Limited and had paid approximately ₹89.23 lakh and ₹86.71 lakh towards the purchase consideration between 2017 and 2021. Although possession was initially represented to be delivered by December 2019 and subsequently by December 2020, the project remained incomplete. Consequently, the applicants sought refund and initiated proceedings before the State Consumer Disputes Redressal Commission in July 2022, prior to commencement of the CIRP.

The CIRP commenced on 24 March 2023. During the CIRP, the applicants submitted their claims as homebuyers, which were admitted by the Resolution Professional. They subsequently informed the Resolution Professional that they were unwilling to pay the balance consideration and did not wish to continue with the project. Their grievance was principally directed against the resolution plan on the ground that it did not provide an exit or refund mechanism for homebuyers seeking withdrawal under Section 18 of RERA.

The applicants relied upon Clause 18 of their respective Agreements for Sale, which contemplated refund with interest in the event of failure to deliver possession within the stipulated period. It was contended that the Successful Resolution Applicant (“SRA”), upon taking over the project, would step into the shoes of the erstwhile promoter and would consequently be bound by the contractual and statutory obligations owed to the applicants under RERA.

The resolution plan, however, specifically provided that “no cancellation of the Units by the Homebuyers will be entertained by the Resolution Applicant.” The applicants contended that such a provision amounted to an impermissible unilateral alteration of their contractual and statutory rights.

The Tribunal rejected the contention. It examined the scope of Section 18 of RERA, which enables an allottee, in specified circumstances, to seek return of the amount paid together with interest where the promoter fails to complete the project or is unable to give possession in accordance with the agreement. However, the Tribunal observed that, at the relevant stage, the SRA could not be treated as having stepped into the shoes of the erstwhile promoter.

The Tribunal noted that the resolution plan had not yet been approved by the Adjudicating Authority and, consequently, the SRA had not assumed control of the project. Its obligations to complete the project would arise in accordance with the resolution plan upon its approval. The SRA therefore could not, at that stage, be treated as having assumed all contractual obligations arising from agreements entered into between the applicants and the Corporate Debtor.

The Tribunal further noted that the CoC had considered the applicants' request for refund and had concluded that cancellation of units and consequent refund would adversely affect the cash flows of the Corporate Debtor. The Tribunal also took note of the fact that homebuyers constituted approximately 22.66% of the voting share in the CoC and had approved the resolution plan through their Authorised Representative, whereas the four applicants collectively represented approximately 0.22% voting share.

In this context, the Tribunal emphasised the collective nature of the insolvency resolution process and observed that the SRA ought to be permitted to take over the Corporate Debtor in accordance with the approved resolution framework, without being subjected to liabilities in a manner inconsistent with the resolution plan. The Tribunal also noted that the SRA was not a party to the proceedings and, therefore, relief affecting its rights and obligations could not appropriately be granted without affording it an opportunity of being heard.

Interplay between RERA and IBC

On the interplay between RERA and the IBC, the Tribunal observed that the two enactments operate in distinct fields. While RERA seeks to protect the interests of individual homebuyers and regulate the real estate sector, the IBC provides a collective statutory mechanism for resolution and revival of financially distressed corporate entities.

The Tribunal held that, where the provisions of the two enactments operate inconsistently, Section 238 of the IBC gives the Code overriding effect. Consequently, an individual remedy available to a homebuyer under RERA cannot be enforced in a manner that defeats or undermines the collective insolvency resolution process under the IBC.

The Tribunal also relied upon the statutory framework governing homebuyers as a class of financial creditors. In particular, it referred to Section 25A(3A) of the IBC, under which the Authorised Representative is required to cast votes in accordance with the decision taken by the requisite majority of the homebuyers comprising the relevant class. The Tribunal accordingly held that an individual homebuyer cannot seek treatment contrary to the collective decision of the class merely because such individual homebuyer may otherwise possess a separate remedy under another enactment.

The Tribunal further observed that it could not direct modification of the commercial terms of a resolution plan or compel the CoC or the SRA to renegotiate the terms of the plan.

The Tribunal underscored that the insolvency resolution process under the IBC proceeds on the basis of collective resolution of claims and balancing of the interests of various stakeholders. Since the applicants' claims had already been admitted within the CIRP, they could not insist upon a separate, individualised remedy outside the insolvency framework where such remedy was inconsistent with the resolution plan and the collective decision-making process under the IBC.

The Tribunal also took note of the fact that substantially similar refund claims had earlier been rejected in applications filed by the same applicants in 2024 and that the said orders had not been challenged before the Appellate Tribunal. The earlier orders had consequently attained finality.

In view of the above, the Tribunal found no sufficient ground to interfere with the resolution plan or to direct its reconsideration and accordingly dismissed the application without costs.

Tuesday, 26 March 2024

TSRERA :- The Allottee has an obligation to adhere to the payment schedule as agreed in its Agreement of Sale as per Section 19(6) and non procurement of the Home loan amount cannot put the Builder under financial distress.

The Allottee has an obligation to adhere to the payment schedule as agreed in its Agreement of Sale as per Section 19(6) and non procurement of the  Home loan amount cannot put the  Builder under financial distress. 


Sri Umesh Choudhary Vs/ M/s Alpine Infratech 

COMPLAINT NO.519 OF 2023 decided on 12th Day of March, 2024 

BEFORE TELANGANA STATE REAL ESTATE REGULATORY AUTHORITY


Facts :-

  1. The Complainant booked a flat in August 2021 in the project of the Respondent Builder.
  2. Application Form/Terms and Conditions of Allotment was signed by him.
  3. The Agreement of Sale was executed in the month of January 2022.
  4. Complainant paid 20% of the cost and the balance 80% amount was to be arranged in form of Home loan.
  5. The Project was approved from many nationalized bank but as the Complainant was a Central Government employee so he wanted the Home Loan in the form of House Building Allowance (HBA) from his concerned department. 
  6. That vide e-mail dated 15.04.2022, the Complainant sought for several documents ( a list of 19 documents) from the Respondent Builder to avail HBA loan.
  7. The complete documents were finally given by the builder on 20.02.2023.
  8.  The Builder directed the Complainant to pay the Final due amount by 28.03.2023 else base price will be increased by Rs.200 per sft.
  9. The Complainant offered an interim payment of Rs.5,00,000/-  by first week of May 2023 and the full payment by July 2023.
  10. In May 2023, the Complainant requested the builder to accept the due amount of Rs.25,00,000/-
  11. The Builder refused to accept the amount and stated that they will only accept if the Complainant agreed to make the payment with the revised base rate by Rs. 1000 per sft an increase of  Rs.11,20,000 in total price. 

Complainants Contentions :-

  1. The delay in making payment occurred due to non-handing over of documents in time. hence, management is responsible for such delays.
  2.  The revised increased rate is not acceptable as the delay in making payment did not occur on default of the Complainant. 
  3. Prayed to take needful action against the Respondent Builder as per the applicable rules and regulations and to get the flat at the original agreed rate.
Respondent Builder's Contentions :-
  1. The Complainant in spite of availing discount did not pay the agreed amount on time.
  2. The Complainant initially agreed orally to take loan from various nationalized banks but later in the month of July 2022, started requesting various documents from the Respondent Company
  3. The Complainant made one or the other request for the documents and that too after a lapse of one year and also which were beyond the purview of the Respondent Company and evaded the payments due to the Respondent Company. 
  4. The Respondent Company sent several mails requesting the Complainant to visit the office of the Respondent Company to sort the issue. 
  5. The Complainant failed to perform his part of contractual obligation and did not make the payment as per schedule, that's why the Company is justified in cancelling the booking 
Observations of the Authority :-

  1. In Clause 1.3 of the BBA, the Complainant agreed to make payment as per payment plan set out in Schedule C (Payment Plan).
  2. As per the Payment Schedule annexed to the said Agreement of Sale, the Complainant categorically agreed to payment of the schedule therein. which is not disputed by either party 
  3. in the annexure to the said Payment Schedule, Point No.4 stipulates that prices are subject to change without prior notice upon non confirmation of sale.  
  4.  the Complainant is bound by the same and failure of the Complainant in complying with the payment schedule is derogation of his duty under Section 19(6) of the Act.
  5. the delay in procuring the documents cannot be attributed to the Respondent Builder as the said documents may not readily available with him and he may not be in a position to produce documents such as 
    1. government pleader's certificate, 
    2. estimates, 
    3. permission under Conduct Rules for purchase of site and for construction of the house,
    4.  Notice under Section 26(1) of the Urban Land (Ceiling & Regulation) Act, 1976, etc
  6. Clause 9.3 (ii) of the undated Agreement of Sale executed between the parties clearly stipulates In case of Default by Allottee under the condition listed above continues for a period beyond 2 (two) consecutive months after notice from the Promoter in this regard, the Promoter may cancel the allotment of the [Apartment/Plot] in favor of the Allottee and refund the money paid to him by the allottee by deducting the booking amount and the interest liabilities and this Agreement shall thereupon stand terminated
Order of Authority:-
  1. The Complainant is directed to pay the remaining amounts which is pending as on date as per the payment schedule agreed upon by both the parties within 60 (sixty) days, along with interest of 10.65%.
  2. In the event the Complainant fails to complete such payment, the Respondent is to initiate measures in accordance with the provisions of the Act and Rules thereunder.

Wednesday, 27 December 2023

Bombay High Court - Where Part Occupancy Certificate of a Project was granted under the rules of the Authority, a flat owner can not seek cancellation of it on the ground of violation , affecting the other owners , who may not be a party to the case.

before The Bombay High Court


Sanjay Phulwaria And Others

vs

Mumbai Metropolitan Region Development Authority And Others


Writ Petition Lodging No. 2639 Of 2018 With Notice Of Motion Lodging No. 542 Of 2018, Chamber Summons No. 238 Of 2018


decided on 16-10-2018

Where Part Occupancy Certificate of a Project was granted under the rules of the Authority, a flat owner can not seek cancellation of it on the ground of violation , affecting the other owners , who may not be a party to the case.


Friday, 25 June 2021

Cancellation of allotment after taking 90% of the total sales consideration is unsustainable in the eyes of law

 In the Matter of Gautam Bhatla V/s Vatika limited Complaint no.1208 of 2019 decided on 17.02.2021 before Haryana Real Estate regulatory authority, Panchkula.


it was held that " The Authority is prima facia of the view that Cancellation of allotment after taking 90% of the total sales consideration and without remitting the amount payable to the allottees after deducting earnest money, is unsustainable in the eyes of law"


Monday, 5 April 2021

ONE-SIDED AND UNREASONABLE CLAUSES IN APARTMENT BUYER’S AGREEMENT CONSTITUTES “UNFAIR TRADE PRACTICE” – SUPREME COURT

 In Ireo Grace RealTech Pvt. Ltd. v. Abhishek Khanna & Ors.,CIVIL APPEAL NO. 5785 OF 2019 the Supreme Court of India examined the clauses of the buyers’ agreement and inter alia observed that 

  • the allottees are given a very limited right to cancel the agreement in the event of the clear and unambiguous failure of the warranties of the developers, which leads to frustration of the agreement on that account. 
  • The Court held that the terms of the apartment buyer‘s agreement, having this limited right of cancellation by the buyers are oppressive and wholly one-sided, and would constitute an unfair trade practice under the Section 2(1)(r) of the Consumer Protection Act, 2019 (CP Act).

The Court stated that term “unfair contract” is defined under the CP Act and the
conferment of powers on the State Consumer Fora and the National Commission to
declare contractual terms which are unfair, as null and void, is a statutory recognition of a power which was implicit under the CP Act. Hence, the buyers cannot be bound by such terms in the agreement. It is a welcome judgment to protect the helpless homebuyers who are left at vagaries of the developers who seek to mis-use the legal provisions.