Search This Blog

Translate the Site.

Showing posts with label cancellation. Show all posts
Showing posts with label cancellation. Show all posts

Tuesday, 26 March 2024

TSRERA :- The Allottee has an obligation to adhere to the payment schedule as agreed in its Agreement of Sale as per Section 19(6) and non procurement of the Home loan amount cannot put the Builder under financial distress.

The Allottee has an obligation to adhere to the payment schedule as agreed in its Agreement of Sale as per Section 19(6) and non procurement of the  Home loan amount cannot put the  Builder under financial distress. 


Sri Umesh Choudhary Vs/ M/s Alpine Infratech 

COMPLAINT NO.519 OF 2023 decided on 12th Day of March, 2024 

BEFORE TELANGANA STATE REAL ESTATE REGULATORY AUTHORITY


Facts :-

  1. The Complainant booked a flat in August 2021 in the project of the Respondent Builder.
  2. Application Form/Terms and Conditions of Allotment was signed by him.
  3. The Agreement of Sale was executed in the month of January 2022.
  4. Complainant paid 20% of the cost and the balance 80% amount was to be arranged in form of Home loan.
  5. The Project was approved from many nationalized bank but as the Complainant was a Central Government employee so he wanted the Home Loan in the form of House Building Allowance (HBA) from his concerned department. 
  6. That vide e-mail dated 15.04.2022, the Complainant sought for several documents ( a list of 19 documents) from the Respondent Builder to avail HBA loan.
  7. The complete documents were finally given by the builder on 20.02.2023.
  8.  The Builder directed the Complainant to pay the Final due amount by 28.03.2023 else base price will be increased by Rs.200 per sft.
  9. The Complainant offered an interim payment of Rs.5,00,000/-  by first week of May 2023 and the full payment by July 2023.
  10. In May 2023, the Complainant requested the builder to accept the due amount of Rs.25,00,000/-
  11. The Builder refused to accept the amount and stated that they will only accept if the Complainant agreed to make the payment with the revised base rate by Rs. 1000 per sft an increase of  Rs.11,20,000 in total price. 

Complainants Contentions :-

  1. The delay in making payment occurred due to non-handing over of documents in time. hence, management is responsible for such delays.
  2.  The revised increased rate is not acceptable as the delay in making payment did not occur on default of the Complainant. 
  3. Prayed to take needful action against the Respondent Builder as per the applicable rules and regulations and to get the flat at the original agreed rate.
Respondent Builder's Contentions :-
  1. The Complainant in spite of availing discount did not pay the agreed amount on time.
  2. The Complainant initially agreed orally to take loan from various nationalized banks but later in the month of July 2022, started requesting various documents from the Respondent Company
  3. The Complainant made one or the other request for the documents and that too after a lapse of one year and also which were beyond the purview of the Respondent Company and evaded the payments due to the Respondent Company. 
  4. The Respondent Company sent several mails requesting the Complainant to visit the office of the Respondent Company to sort the issue. 
  5. The Complainant failed to perform his part of contractual obligation and did not make the payment as per schedule, that's why the Company is justified in cancelling the booking 
Observations of the Authority :-

  1. In Clause 1.3 of the BBA, the Complainant agreed to make payment as per payment plan set out in Schedule C (Payment Plan).
  2. As per the Payment Schedule annexed to the said Agreement of Sale, the Complainant categorically agreed to payment of the schedule therein. which is not disputed by either party 
  3. in the annexure to the said Payment Schedule, Point No.4 stipulates that prices are subject to change without prior notice upon non confirmation of sale.  
  4.  the Complainant is bound by the same and failure of the Complainant in complying with the payment schedule is derogation of his duty under Section 19(6) of the Act.
  5. the delay in procuring the documents cannot be attributed to the Respondent Builder as the said documents may not readily available with him and he may not be in a position to produce documents such as 
    1. government pleader's certificate, 
    2. estimates, 
    3. permission under Conduct Rules for purchase of site and for construction of the house,
    4.  Notice under Section 26(1) of the Urban Land (Ceiling & Regulation) Act, 1976, etc
  6. Clause 9.3 (ii) of the undated Agreement of Sale executed between the parties clearly stipulates In case of Default by Allottee under the condition listed above continues for a period beyond 2 (two) consecutive months after notice from the Promoter in this regard, the Promoter may cancel the allotment of the [Apartment/Plot] in favor of the Allottee and refund the money paid to him by the allottee by deducting the booking amount and the interest liabilities and this Agreement shall thereupon stand terminated
Order of Authority:-
  1. The Complainant is directed to pay the remaining amounts which is pending as on date as per the payment schedule agreed upon by both the parties within 60 (sixty) days, along with interest of 10.65%.
  2. In the event the Complainant fails to complete such payment, the Respondent is to initiate measures in accordance with the provisions of the Act and Rules thereunder.

Wednesday, 27 December 2023

Bombay High Court - Where Part Occupancy Certificate of a Project was granted under the rules of the Authority, a flat owner can not seek cancellation of it on the ground of violation , affecting the other owners , who may not be a party to the case.

before The Bombay High Court


Sanjay Phulwaria And Others

vs

Mumbai Metropolitan Region Development Authority And Others


Writ Petition Lodging No. 2639 Of 2018 With Notice Of Motion Lodging No. 542 Of 2018, Chamber Summons No. 238 Of 2018


decided on 16-10-2018

Where Part Occupancy Certificate of a Project was granted under the rules of the Authority, a flat owner can not seek cancellation of it on the ground of violation , affecting the other owners , who may not be a party to the case.


Friday, 25 June 2021

Cancellation of allotment after taking 90% of the total sales consideration is unsustainable in the eyes of law

 In the Matter of Gautam Bhatla V/s Vatika limited Complaint no.1208 of 2019 decided on 17.02.2021 before Haryana Real Estate regulatory authority, Panchkula.


it was held that " The Authority is prima facia of the view that Cancellation of allotment after taking 90% of the total sales consideration and without remitting the amount payable to the allottees after deducting earnest money, is unsustainable in the eyes of law"


Monday, 5 April 2021

ONE-SIDED AND UNREASONABLE CLAUSES IN APARTMENT BUYER’S AGREEMENT CONSTITUTES “UNFAIR TRADE PRACTICE” – SUPREME COURT

 In Ireo Grace RealTech Pvt. Ltd. v. Abhishek Khanna & Ors.,CIVIL APPEAL NO. 5785 OF 2019 the Supreme Court of India examined the clauses of the buyers’ agreement and inter alia observed that 

  • the allottees are given a very limited right to cancel the agreement in the event of the clear and unambiguous failure of the warranties of the developers, which leads to frustration of the agreement on that account. 
  • The Court held that the terms of the apartment buyer‘s agreement, having this limited right of cancellation by the buyers are oppressive and wholly one-sided, and would constitute an unfair trade practice under the Section 2(1)(r) of the Consumer Protection Act, 2019 (CP Act).

The Court stated that term “unfair contract” is defined under the CP Act and the
conferment of powers on the State Consumer Fora and the National Commission to
declare contractual terms which are unfair, as null and void, is a statutory recognition of a power which was implicit under the CP Act. Hence, the buyers cannot be bound by such terms in the agreement. It is a welcome judgment to protect the helpless homebuyers who are left at vagaries of the developers who seek to mis-use the legal provisions.