IN THE MATTER OF: M/s. Imperia Structures Ltd. Vs. Anil Patni
and Another (Decided by Hon’ble Supreme Court of India on
02.11.2020)
Issues:
1. Whether the remedies available to the consumers under
provisions of the Consumer Protection Act, 1986 (“CP Act”)
would be additional remedies, not barred by the coming in
force of the Real Estate (Regulation and Development) Act,
2016 (“RERA Act”)?
2. Whether the provisions of the RERA Act have made any
change in the legal position with regards to remedies
available to the Allottees?
3. Whether the entitlement of the Allottee has to be reckoned
in terms of the date of Agreement or the RERA registration
date?
Facts:
1. A Housing Scheme called “The ESFERA” in Gurgaon, Haryana
was launched by the Appellant in 2011. All the Complainants
booked their respective apartments by paying the requisite
booking amounts and thereafter executed the Builder Buyer
Agreement towards their individual units. The Agreement
provided for delay due to reasons beyond the control of the
Developer (Appellant) and failure to deliver possession due
to Govt. Rules/Notifications, etc under the Force Majeure
clause and the compensation thereof. Even after four yearsthere was no sign of Project getting completed. Thereafter,
in 2017, the Project was registered with Haryana Real Estate
Regulatory Authority, Panchkula (“HRERA”).
2. The Consumer Complaint was filed by the Complainants for
the delay in handing over of the possession of their
respective apartments. In response, the Appellant
challenged the jurisdiction of the National Consumer
Dispute Redressal Commission (“National Commission”) on
the ground that the Complainants/Respondents would not
come within the definition of consumers. After having heard
the submissions, the Commission allowed the Complaint
and granted relief of refund to the
Complainants/Respondents.
3. The Appellant aggrieved by the order of the National
Commission, preferred an appeal under Section 23 of the CP
Act before the Hon’ble Supreme Court.
Court’s Observations:
• The Counsel for Appellants submitted that once the RERA
Act came into force, all questions concerning the Project
including issues relating to construction and completion
thereof, would be under the exclusive control and
jurisdiction of the authorities under RERA Act. The National
Commission, therefore, ought not to have entertained the
Consumer Complaint. Further, the Registration Certificate
being valid upto 31.12.2020, the Appellant could not be
said to have delayed the construction and consequently,
there could be no finding that there was deficiency on part
of the Appellant. The Counsel for the Respondents
submitted that whether the delay occurred due to force
majeure was already dealt by the National Commission and
no reasonable explanation was available on record to
dislodge that finding. It was further submitted that the
remedy afforded by the CP Act would be an additional
remedy to a consumer and such legal position remained
unchained even after the enactment of the RERA Act.
• The Court noted that conclusions drawn by the National
Commission that – i) all the Complainants were consumers
within the meaning of the Act; and ii) there was delay on
part of the Appellant in completion the construction within
time, are absolutely correct and does not call for
interference of this Hon’ble Court.
• While discussing various precedents, the Court observed
that the Hon’ble Apex Court has consistently held that the
remedies available under the provisions of the CP Act are
additional remedies over and above the other remedies
including those made available under any special statutes;and that the availability of an alternate remedy is no bar in
entertaining a complaint under the CP Act. The Hon’ble
court further observed that insofar as cases where such
proceedings under the CP Act are initiated after the
provisions of the RERA Act came into force, there is nothing
in the RERA Act which bars such initiation. The absence of
bar under Section 79 to the initiation of proceedings before
a fora which cannot be called a Civil Court and express
saving under Section 88 of the RERA Act, make the position
quite clear. Furthermore, Section 18 itself specifies that the
remedy under said Section is "without prejudice to any
other remedy available". Thus, the parliamentary intent is
clear that a choice or discretion is given to the allottee
whether he wishes to initiate appropriate proceedings
under the CP Act or file an application under the RERA Act.
• The Court held that in the present case the apartments
were booked by the Complainants in 2011-2012 and the
Builder Buyer Agreements were entered into in November,
2013. As promised, the construction should have been
completed in 42 months. The period had expired well
before the Project was registered under the provisions of
the RERA Act. Merely because the registration under the
RERA Act is valid till 31.12.2020 does not mean that the
entitlement of the concerned Allottees to maintain an
action stands deferred. It is relevant to note that even for
the purposes of Section 18, the period has to be reckoned
in terms of the agreement and not the registration.
Therefore, the entitlement of the Complainants must be
considered in the light of the terms of the Builder Buyer
Agreements and was rightly dealt with by the Commission.
The Hon’ble Court dismissed the appeal, affirming the view
taken by the National Commission.