Thursday, 1 August 2024

MahaRERA - To ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.

 MahaRERA - To ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.


Anil Kumar Dattani Versus Real Gem Buildtech Private Limited & Ors. Complaint No. CC006000000292852 Before the Maharashtra Real Estate Regulatory Authority Mumbai Decided on 13th May 2024)


Fact of the Case :-

  • Respondent no. 1 i.e. Realgem Buildtech Private Limited  is the Promoter of the project.
  • Respondent no. 2 i.e. Bhishma Realty Limited is the landowner of the project.
  • Respondent no. 3 i.e Kindmaker Developers Private Limited  has been appointed as a Development Manager under the development management agreement dated 18-03-2018 and is basically an agent of the respondent no. 1 functioning for a fixed fee. the respondent no. 3 was appointed for the purposes of 
    • inter alia managing, 
    • monitoring, 
    • supervising and 
    • coordinating the construction and 
    • development of the said project 
    • together with the sales and marketing related activities including customer relationship management.

  • The subject matter of the case is flat bearing no. 2302 on 23rd floor in the “RUSTOMJEE CROWN - PHASE I" at Prabhadevi, Mumbai.
  • On 16-01-2019 The respondent issued  the allotment letter in the complainant's name. 
  • On 25-01-2019 The complainant and the respondents entered into a registered agreement for sale.
  • The respondent had assured to handover the possession of the said flat on 31-12-2021.
  • The Flat was for a total consideration of Rs. 7,69,86,000/-
  • The Complainant has already paid Rs. 7,41,83,995/- to the respondents from time to time..
  • The respondent did not give the possession by the said date.
  • On 27-09-2022 the complainant filed the present complaint..

Submissions by Appellant:-

  • As per the RERA, the all 3 respondents are jointly and severally liable as per circular no. 12/2017 dated 04-12-2017.

Submissions by Respondent(s):

  • The date of possession mentioned in the agreement for sale is 31-12-2021 and the same was subject to provisions of clause 8 of the said agreement which provides for a reasonable extension on occurrence of mitigating events.
  • The Covid 19 pandemic was a force majeure event and therefore covered under clause 8 of the agreement for sale. 

Observations made by the Hon’ble Court:-

  • the Respondent nos. 1 and 2 being the promoters of this project registered with the MahaRERA are liable to perform their part as stipulated in the registered agreement for sale dated 25-01-2019 signed with the complainant herein.
  • With regards to respondent taking the plea on the issue of jurisdiction as per clause 16.1 of the said agreement for sale wheras the complainant has agreed for arbitration in case of any dispute arising in respect of the said agreement for sale.MahaRERA is of the view that the same is raised at a belated stage by filing its reply on record of MahaRERA,
  • Further, there are no explicit provisions under RERA about the arbitration clause. Hence,the same stands rejected.
  • As far as the issue raised by the complainant about GST input credit not being provided to him, the MahaRERA is of the prima facie view that the same does not fall within the purview of the MahaRERA under the provisions of the RERA. 
  • However, it is for the concerned competent forum to deal with such issues. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST. 
  • The MahaRERA is not going to deal with the said issue for want of jurisdiction.
  • the MahaRERA is of the view that the delay cited by the respondent such as delay in obtaining CFO NOC due to change in fire norms and the delay in obtaining NOC from MPCB do not fall within the force majeure factors mentioned in the draft model agreement for sale prescribed under the RERA and the relevant rules made thereunder.

Court’s Order:-

  • The respondent promoter is directed to pay interest for the delayed possession to the complainants from 01-01-2023 ( as per agreements for sale i.e. 31-12-2021 + 1 year grace period due to Covid-19 Pandemic i.e. 31-12-2022) for every month till the actual date of possession of the said flat to the complainant or till the date of offer of possession with OC if any obtained by the respondent promoter. 
  • to ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.

MAHA RERA - The delay in obtaining NOCs including Fire NOC do not fall within the force majeure factors prescribed under the RERA and the relevant rules made thereunder.

 MAHA RERA - The delay in obtaining NOCs  including Fire NOC do not fall within the force majeure factors prescribed under the RERA and the relevant rules made thereunder.


Anil Kumar Dattani Versus Real Gem Buildtech Private Limited & Ors. Complaint No. CC006000000292852 Before the Maharashtra Real Estate Regulatory Authority Mumbai Decided on 13th May 2024)


Fact of the Case :-

  • Respondent no. 1 i.e. Realgem Buildtech Private Limited  is the Promoter of the project.
  • Respondent no. 2 i.e. Bhishma Realty Limited is the landowner of the project.
  • Respondent no. 3 i.e Kindmaker Developers Private Limited  has been appointed as a Development Manager under the development management agreement dated 18-03-2018 and is basically an agent of the respondent no. 1 functioning for a fixed fee. the respondent no. 3 was appointed for the purposes of 
    • inter alia managing, 
    • monitoring, 
    • supervising and 
    • coordinating the construction and 
    • development of the said project 
    • together with the sales and marketing related activities including customer relationship management.

  • The subject matter of the case is flat bearing no. 2302 on 23rd floor in the “RUSTOMJEE CROWN - PHASE I" at Prabhadevi, Mumbai.
  • On 16-01-2019 The respondent issued  the allotment letter in the complainant's name. 
  • On 25-01-2019 The complainant and the respondents entered into a registered agreement for sale.
  • The respondent had assured to handover the possession of the said flat on 31-12-2021.
  • The Flat was for a total consideration of Rs. 7,69,86,000/-
  • The Complainant has already paid Rs. 7,41,83,995/- to the respondents from time to time..
  • The respondent did not give the possession by the said date.
  • On 27-09-2022 the complainant filed the present complaint..

Submissions by Appellant:-

  • As per the RERA, the all 3 respondents are jointly and severally liable as per circular no. 12/2017 dated 04-12-2017.

Submissions by Respondent(s):

  • The date of possession mentioned in the agreement for sale is 31-12-2021 and the same was subject to provisions of clause 8 of the said agreement which provides for a reasonable extension on occurrence of mitigating events.
  • The Covid 19 pandemic was a force majeure event and therefore covered under clause 8 of the agreement for sale. 

Observations made by the Hon’ble Court:-

  • the Respondent nos. 1 and 2 being the promoters of this project registered with the MahaRERA are liable to perform their part as stipulated in the registered agreement for sale dated 25-01-2019 signed with the complainant herein.
  • With regards to respondent taking the plea on the issue of jurisdiction as per clause 16.1 of the said agreement for sale wheras the complainant has agreed for arbitration in case of any dispute arising in respect of the said agreement for sale.MahaRERA is of the view that the same is raised at a belated stage by filing its reply on record of MahaRERA,
  • Further, there are no explicit provisions under RERA about the arbitration clause. Hence,the same stands rejected.
  • As far as the issue raised by the complainant about GST input credit not being provided to him, the MahaRERA is of the prima facie view that the same does not fall within the purview of the MahaRERA under the provisions of the RERA. 
  • However, it is for the concerned competent forum to deal with such issues. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST. 
  • The MahaRERA is not going to deal with the said issue for want of jurisdiction.
  • the MahaRERA is of the view that the delay cited by the respondent such as delay in obtaining CFO NOC due to change in fire norms and the delay in obtaining NOC from MPCB do not fall within the force majeure factors mentioned in the draft model agreement for sale prescribed under the RERA and the relevant rules made thereunder.

Court’s Order:-

  • The respondent promoter is directed to pay interest for the delayed possession to the complainants from 01-01-2023 ( as per agreements for sale i.e. 31-12-2021 + 1 year grace period due to Covid-19 Pandemic i.e. 31-12-2022) for every month till the actual date of possession of the said flat to the complainant or till the date of offer of possession with OC if any obtained by the respondent promoter. 
  • to ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.

Maha RERA - Issue of GST input credit does not fall within the purview of the provisions of the RERA. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST.

Issue of  GST input credit does not fall within the purview of the  provisions of the RERA. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST.  


Anil Kumar Dattani Versus Real Gem Buildtech Private Limited & Ors. Complaint No. CC006000000292852 Before the Maharashtra Real Estate Regulatory Authority Mumbai Decided on 13th May 2024)


Fact of the Case :-

  • Respondent no. 1 i.e. Realgem Buildtech Private Limited  is the Promoter of the project.
  • Respondent no. 2 i.e. Bhishma Realty Limited is the landowner of the project.
  • Respondent no. 3 i.e Kindmaker Developers Private Limited  has been appointed as a Development Manager under the development management agreement dated 18-03-2018 and is basically an agent of the respondent no. 1 functioning for a fixed fee. the respondent no. 3 was appointed for the purposes of 
    • inter alia managing, 
    • monitoring, 
    • supervising and 
    • coordinating the construction and 
    • development of the said project 
    • together with the sales and marketing related activities including customer relationship management.

  • The subject matter of the case is flat bearing no. 2302 on 23rd floor in the “RUSTOMJEE CROWN - PHASE I" at Prabhadevi, Mumbai.
  • On 16-01-2019 The respondent issued  the allotment letter in the complainant's name. 
  • On 25-01-2019 The complainant and the respondents entered into a registered agreement for sale.
  • The respondent had assured to handover the possession of the said flat on 31-12-2021.
  • The Flat was for a total consideration of Rs. 7,69,86,000/-
  • The Complainant has already paid Rs. 7,41,83,995/- to the respondents from time to time..
  • The respondent did not give the possession by the said date.
  • On 27-09-2022 the complainant filed the present complaint..

Submissions by Appellant:-

  • As per the RERA, the all 3 respondents are jointly and severally liable as per circular no. 12/2017 dated 04-12-2017.

Submissions by Respondent(s):

  • The date of possession mentioned in the agreement for sale is 31-12-2021 and the same was subject to provisions of clause 8 of the said agreement which provides for a reasonable extension on occurrence of mitigating events.
  • The Covid 19 pandemic was a force majeure event and therefore covered under clause 8 of the agreement for sale. 

Observations made by the Hon’ble Court:-

  • the Respondent nos. 1 and 2 being the promoters of this project registered with the MahaRERA are liable to perform their part as stipulated in the registered agreement for sale dated 25-01-2019 signed with the complainant herein.
  • With regards to respondent taking the plea on the issue of jurisdiction as per clause 16.1 of the said agreement for sale wheras the complainant has agreed for arbitration in case of any dispute arising in respect of the said agreement for sale.MahaRERA is of the view that the same is raised at a belated stage by filing its reply on record of MahaRERA,
  • Further, there are no explicit provisions under RERA about the arbitration clause. Hence,the same stands rejected.
  • As far as the issue raised by the complainant about GST input credit not being provided to him, the MahaRERA is of the prima facie view that the same does not fall within the purview of the MahaRERA under the provisions of the RERA. 
  • However, it is for the concerned competent forum to deal with such issues. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST. 
  • The MahaRERA is not going to deal with the said issue for want of jurisdiction.
  • the MahaRERA is of the view that the delay cited by the respondent such as delay in obtaining CFO NOC due to change in fire norms and the delay in obtaining NOC from MPCB do not fall within the force majeure factors mentioned in the draft model agreement for sale prescribed under the RERA and the relevant rules made thereunder.

Court’s Order:-

  • The respondent promoter is directed to pay interest for the delayed possession to the complainants from 01-01-2023 ( as per agreements for sale i.e. 31-12-2021 + 1 year grace period due to Covid-19 Pandemic i.e. 31-12-2022) for every month till the actual date of possession of the said flat to the complainant or till the date of offer of possession with OC if any obtained by the respondent promoter. 
  • to ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.

Maha RERA - There are no explicit provisions under RERA about the arbitration clause in agreement for Sale

There are no explicit provisions under RERA about the arbitration clause in agreement for Sale 

Anil Kumar Dattani Versus Real Gem Buildtech Private Limited & Ors. Complaint No. CC006000000292852 Before the Maharashtra Real Estate Regulatory Authority Mumbai Decided on 13th May 2024)


Fact of the Case :-

  • Respondent no. 1 i.e. Realgem Buildtech Private Limited  is the Promoter of the project.
  • Respondent no. 2 i.e. Bhishma Realty Limited is the landowner of the project.
  • Respondent no. 3 i.e Kindmaker Developers Private Limited  has been appointed as a Development Manager under the development management agreement dated 18-03-2018 and is basically an agent of the respondent no. 1 functioning for a fixed fee. the respondent no. 3 was appointed for the purposes of 
    • inter alia managing, 
    • monitoring, 
    • supervising and 
    • coordinating the construction and 
    • development of the said project 
    • together with the sales and marketing related activities including customer relationship management.

  • The subject matter of the case is flat bearing no. 2302 on 23rd floor in the “RUSTOMJEE CROWN - PHASE I" at Prabhadevi, Mumbai.
  • On 16-01-2019 The respondent issued  the allotment letter in the complainant's name. 
  • On 25-01-2019 The complainant and the respondents entered into a registered agreement for sale.
  • The respondent had assured to handover the possession of the said flat on 31-12-2021.
  • The Flat was for a total consideration of Rs. 7,69,86,000/-
  • The Complainant has already paid Rs. 7,41,83,995/- to the respondents from time to time..
  • The respondent did not give the possession by the said date.
  • On 27-09-2022 the complainant filed the present complaint..

Submissions by Appellant:-

  • As per the RERA, the all 3 respondents are jointly and severally liable as per circular no. 12/2017 dated 04-12-2017.

Submissions by Respondent(s):

  • The date of possession mentioned in the agreement for sale is 31-12-2021 and the same was subject to provisions of clause 8 of the said agreement which provides for a reasonable extension on occurrence of mitigating events.
  • The Covid 19 pandemic was a force majeure event and therefore covered under clause 8 of the agreement for sale. 

Observations made by the Hon’ble Court:-

  • the Respondent nos. 1 and 2 being the promoters of this project registered with the MahaRERA are liable to perform their part as stipulated in the registered agreement for sale dated 25-01-2019 signed with the complainant herein.
  • With regards to respondent taking the plea on the issue of jurisdiction as per clause 16.1 of the said agreement for sale wheras the complainant has agreed for arbitration in case of any dispute arising in respect of the said agreement for sale.MahaRERA is of the view that the same is raised at a belated stage by filing its reply on record of MahaRERA,
  • Further, there are no explicit provisions under RERA about the arbitration clause. Hence,the same stands rejected.
  • As far as the issue raised by the complainant about GST input credit not being provided to him, the MahaRERA is of the prima facie view that the same does not fall within the purview of the MahaRERA under the provisions of the RERA. 
  • However, it is for the concerned competent forum to deal with such issues. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST. 
  • The MahaRERA is not going to deal with the said issue for want of jurisdiction.
  • the MahaRERA is of the view that the delay cited by the respondent such as delay in obtaining CFO NOC due to change in fire norms and the delay in obtaining NOC from MPCB do not fall within the force majeure factors mentioned in the draft model agreement for sale prescribed under the RERA and the relevant rules made thereunder.

Court’s Order:-

  • The respondent promoter is directed to pay interest for the delayed possession to the complainants from 01-01-2023 ( as per agreements for sale i.e. 31-12-2021 + 1 year grace period due to Covid-19 Pandemic i.e. 31-12-2022) for every month till the actual date of possession of the said flat to the complainant or till the date of offer of possession with OC if any obtained by the respondent promoter. 
  • to ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.

Wednesday, 23 June 2021

P&H High Court - The intent of the advisory issued by the Government of India was certainly not to accommodate such defaulters

 The Ministry of Housing and Urban Affairs (MOHUA) in its Office Memorandum dated 13 May 2020 (Advisory) has declared the current pandemic as a force majeure event for the purposes of Real Estate (Regulation and Development) Act 2016 (RERA) and extended the timelines for registration and completion of real estate projects.


The circular dated 13.5.2020 issued by Real Estate Regulatory Authority, Punjab (RERA) whereby it extended the period of validity of registration of projects by six months was challenged in the Punjab and Haryana High Court in the Matter of Vinod Kumar v. Union of India and others CWP-8781-2020 decided on dated 30.06.2020 whereas the High court held that “we are not impressed by the argument. We fail to understand the need for passing a omnibus order giving protection to all the projects in State of Punjab, particularly when the Act has a specific provision for entertaining an application on behalf of the promoter/builder for extension of time. There is no doubt that 'Force Majeure' clause can be invoked for this purpose. However, the applicant who would approach the RERA would have to convince it that he has been forced by circumstances beyond his control to continue with the Project. Surprisingly, the circular may even give protection to those promoters/builders whose registration may have expired long back. The intent of the advisory issued by the Government of India was certainly not to accommodate such defaulters. We, thus, find something palpably wrong with the circular. Thus, operation of impugned circular dated 13.5.2020 (Annexure P-1) is hereby stayed.


Friday, 21 May 2021

NCDRC - Wherever the builder commits a particular date or time frame for completion of the construction and offering possession to the buyer, he must necessarily honour the commitment made by him, If the builder can indefinitely postpone and delay the construction of the flat and the flat buyer has no option but to wait till the builder decides to complete the construction and offer possession to the buyer, that would be nothing but a travesty of justice.

 In the Matter of Pradeep Narula & Anr. Vs. M/s. Granite Gate Properties Pvt. Ltd. & Anr. Complaint no. Consumer Case No. 315 OF 2014 decided on 23.08.2016 before National Consumer Disputes Redressal Commission


The NCDRC in this case Observed that 


"10.   ...........  The primary purpose of a consumer in booking a residential flat which the builder is to construct for him, is to start living in that house on or about the date committed to him by the builder for delivering possession of the flat booked by him.  If the builder does not deliver upon his contractual obligation and at the same time, is unable to show that the delay in completion of the flat and offering its possession to the consumer was on account on circumstances beyond his control, this would constitute deficiency on the part of the builder / service provider in rendering services to the consumer.  If I accept the contention that the builder can indefinitely postpone and delay the construction of the flat and the flat buyer has no option but to wait till the builder decides to complete the construction and offer possession to the buyer, that would be nothing but a travesty of justice and result in a situation where the flat buyer is left at the mercy of the builder, without recourse to an appropriate legal remedy.  Such an interpretation, if taken, is bound to defeat the very objective behind the enactment of the Consumer Protection Act, as far as housing construction is concerned.  Therefore, I am unable to accept the contention advanced by the learned counsel for the opposite party.  In my view, wherever the builder commits a particular date or time frame for completion of the construction and offering possession to the buyer, he must necessarily honour the commitment made by him, though a minor delay may not constitute deficiency in the service rendered by him to the buyer.  Of course, if the builder is able to how that the delay in completion of the construction and offering possession to the buyer is attributable wholly to the circumstances beyond his control, that may not be a case of deficiency in the services rendered to the consumer".

Monday, 5 April 2021

SPECIFIED “DATE OF POSSESSION” IS BINDING ON THE DEVELOPER AND NOT AFFECTED BY “GRACE PERIOD” CLAUSES UNDER Agreement For Sales

 In Suryakant Yashwant Jadhav & Anr. v. Bellissimo Hi-Rise Builders Pvt. Ltd. & Ors., the MahaRera Appellate Tribunal has held that 

  • where the promoters had agreed to give possession with occupancy certificate on a specified date, the promoters were obligated under Section 19(10) of RERA to offer physical possession with occupancy certificate to allottees and the allottees were obligated to take such physical possession with occupancy certificate within two months of such delivery. 
  • The Court said that failure to handover physical possession of the flat with occupancy certificate, would attract Section 18 of RERA With respect to the clause of “grace period” of one year (which was provided irrespective of the force majeure events or situations beyond control of the parties) contained in the Agreement for Sale (AFS), 
  • The Tribunal held that Section 18 of RERA is absolute on the point of "specified date" mentioned in the agreement for giving possession and cannot be extended on the basis of such grace period. 
  • The Tribunal held that upholding the ‘grace period’ clause of the AFS would be against the spirit of Section 18 of RERA and consequently against the object of safeguarding interest of customers.