Search This Blog

Translate the Site.

Sunday, 27 June 2021

No Occupancy Certificate: Not The Only Criteria For Registration With RERA

 The Maharashtra Real Estate Regulatory Authority (MahaRERA) in its recent order has held that mere non-procurement of an occupancy certificate by a developer does not make the developer liable to register the real estate project1 under Section 3 of the Real Estate (Regulation and Development) Act, 2016 (Act).


This order has been passed following a complaint filed by Sulatana Dalal (Complainant) against Asia Group (Developer), before MahaRERA in relation to a project named as 'Miracle Mall' situated at Bhiwandi, Thane, Maharashtra. The Complainant's contention was that even though the building was completely occupied, the Developer had failed to obtain an occupation certificate and committed breach of law. Against this background, the Complainant sought directions from MahaRERA to register the building under the provisions of the Act. 

MahaRERA's Position On The Dispute

In the instant case, the Developer contended that all units of the concerned project were constructed after obtaining due permissions from the concerned authorities and all units in the building were sold to its customers prior to the commencement of the Act. Therefore, the concerned project was not required to be registered under the Act.


MahaRERA while adjudicating the dispute, looked at the pith and substance of the proviso to Section 3 of the Act. The proviso to Section 3 of the Act reads as follows:


"Provided that projects that are ongoing on the date of commencement of this Act and for which the completion certificate has not been issued, the promoter shall make an application to the Authority for registration of the said project within a period of three months from the date of commencement of this Act."


From a bare reading of the proviso, the intention of the legislators appears to clearly include all projects whose construction is ongoing and which have not received a CC. In order to fall within the premise of the aforementioned proviso to Section 3 of the Act, a real estate project is required to satisfy both these conditions – i.e., construction is ongoing and the project has not received a CC.


In the present factual matrix, the project got completed in 2012-13 and the Developer had failed to procure a CC, thereby satisfying only one out of the two conditions for registering a project under the Act. Note that the State of Maharashtra does not have a framework for issuance of a CC by its own competent authority, so the present order uses the terms 'completion certificate' and 'occupancy certificate' interchangeably.


In the instant case, the MahaRERA held that mere non-procurement of an OC will not trigger a registration requirement under the Act and dismissed the complaint with the following observations:


There was no ongoing construction activity in the project, where the Complainant resides.

The building where the Complainant resides had been occupied prior to the commencement of the Act and hence no registration under the Act is required.