Search This Blog

Translate the Site.

Tuesday, 18 May 2021

The complaints under Section 12 were thus held to be required to be filed only before the Adjudicating Officer, being the authority empowered to grant compensation under the Act

 In the Matter of Sandeep Mann vs. Real Estate Regulatory Authority, Punjab and Anr. Complaint no. Appeal No. 53 of 2018 decided on 27.02.2019 before  Punjab Real Estate Appellate Tribunal


The issue that arose in the batch matter of fifteen appeals was as to the forum (as between the Real Estate Regulatory Authority constituted under Section 20, and the Adjudicating Officer appointed under Section 71) before which a person aggrieved by violations and contraventions enumerated in Section 11(5), 12, 14(3), 18(1), 18(2), 18(3), 19(4) and 19(7) of the RERA, 2016 or the agreement for sale, praying for reliefs of refund, return of investment including compensation, setting aside of order of cancellation of allotment, compensation, compensation and interest, compensation or interest and interest as a separate relief may file a complaint.The question arose on account of two circulars issued by the Authority declaring that complaints for compensation shall be filed before and adjudged by the Adjudicating Officer whereas all other complaints shall be filed before and adjudicated by the Authority. Following these circulars, one set of orders came to be passed by the Adjudicating Officer, whereby the complaints claiming relief of refund, interest and compensation came to be dismissed for lack of jurisdiction. Another set of orders were those which the Authority passed, rejecting the complaints which alleged

violations and contraventions of the Act, while granting liberty to approach the Adjudicating Officer. All these orders were subject matter of the appeal decided by the Appellate Tribunal.

The Appellate Tribunal after considering the provisions of the Act came to the conclusion that:


(i) In case of Section 11(5), no difficulty arose, in view of the fact that the said provision specifically mentioned the Authority as the forum, before which a complaint could be filed by a complainant aggrieved by cancellation of allotment by the promoter;

 

(ii) Section 12 provides for compensation on account of false advertisement, and also for refund of investment along with interest, in case of a complainant who desires to withdraw from the project on account of false advertisement. The nature of relief being different, the circulars issued by the Authority provided for adjudication of the complaint based on the same cause of action (viz., false advertisement) by two different authorities (viz., the Adjudicating Officer for compensation and the Authority for refund of investment). The Appellate Tribunal held this mechanism to be flawed, inter alia, on account of the fact that it raised the possibility of differing orders being passed by the two authorities. Further, the cause of action being the same, the fact that the complainant had a choice of relying would not change the nature of the proceedings. The basis of the proceedings was adjudication of the proof of default. The complaints under Section 12 were thus held to be required to be filed only before the Adjudicating Officer, being the authority empowered to grant compensation under the Act;


(iii) Section 14(3), like Section 11(3), was held not to pose any problem on account of the fact that the use of the words ‘shall be entitled to receive appropriate compensation in the manner as provided under this Act’ could only mean that the appropriate forum was the Adjudicating Officer, viz., the authority empowered to award compensation under the Act;


(iv) Section 18(1), the cause of action for which is the inability of the promoter to give possession due to any of the reasons specified therein, provides an option to the buyer to withdraw from the project and seek return of investment with interest including compensation in the manner prescribed in the Act, thereby meaning that the Adjudicating Officer shall have power to adjudicate the complaint. In a case covered by the proviso, however, viz., one where return of investment is not sought and the allottee is entitled to interest till possession, the appropriate forum was the Authority; (v) Sections 18(2) and (3) provide for compensation in terms of the Act for the default of the promoter for the reasons specified therein, and therefore the appropriate forum was the Adjudicating Officer, it was held by the Appellate Tribunal;


(vi) A complaint under Section 19(4), which made a reference to award of compensation, was held to be required to be placed before the Adjudicating Officer, while one under Section 19(7), which imposed a liability upon the allottee to pay interest on delayed payments to the promoter, was required to be filed before the Authority.


Based on the above findings, the appeals came to be allowed. The Appellate Tribunal did however clarify that the decision of the Tribunal was not to apply to matters which had attained finality. The pending complaints/ applications were to be transferred to the appropriate forum as per the findings set out above.


The Complete order can be accessed at https://rera.punjab.gov.in/pdf/OrdersJudgementsPbAT/20190405PbATAppealNo11to56of2018.pdf