Provisions of Section 12 are retroactive in nature,allottees are entitled to protection for breaches and failure of the developer notwithstanding that the transactions between the developer and the allottees consummated before the Act came into force

 In the Matter of Rohit Chawla and Ors. vs. Bombay Dyeing & Mfg. Co. Ltd. complaint no.AT006000000011016  decided on 31.12.2019 before Maharashtra Real Estate Appellate Tribunal


In the instant case, 

  • the developer had published the project and gave assurances regarding details of the amenities and flats and basis such representations, the allottees booked flats in the project in 2012-2013. 

  • The developer further represented to the allottees that it would handover the possession of the flat by 2017. However, the developer failed to handover the possession and also failed to provide amenities as were assured to the allottees. 

  • Accordingly, the allottees filed a complaint before MahaRERA claiming that they had suffered a loss on account of incorrect and false statements made by the developer in relation to the project. Further, the allottees also sought refunds of the amounts paid by them along with interest thereon.

  • MahaRERA held that Section 12 of the Act (which deals with obligations of the developer regarding veracity of the advertisement or prospectus) was not retrospective and was not applicable to the instant case since the allottees had booked flats in the year 2012-2013 and the Act came into force in the year 2017. 

  • Further, MahaRERA had rejected the plea of the allottees to withdraw from the project since it would jeopardise the completion of the project. 

  • The MahaRERA Appellate Tribunal overruled the order passed by MahaRERA and held that provisions of Section 12 (which deals with obligations of the developer regarding veracity of the advertisement or prospectus) are retroactive in nature and the allottees are entitled to protection for breaches and failure of the developer notwithstanding that the transactions between the developer and the allottees consummated before the Act came into force.

  •  Further, MahaRERA Appellate Tribunal also held that the allottees are entitled to withdraw from the project and the developer was under an obligation to refund the amounts paid by the allottees along with interest thereon.