Once registration of the Real Estate project lapses on non-completion of project or on revocation,the Authority is enjoined upon the duty to consult with the appropriate Government to take such action as it may deem including the carrying out of the remaining development works by competent authority or by the association of allottees or any other manner

 In the Matter of  Bikram Chatterji vs Union Of India Complaint no. WRIT PETITION (C) NO.940/2017 decided on  23.07.2019 before Supreme Court of India


The Supreme Court Observed that


112. Once registration lapses on non-completion of project within the time stipulated or it is revoked the consequence ensue as enumerated in Section 8 of RERA, the Authority is enjoined upon the duty to consult with the appropriate Government to take such action as it may deem including the carrying out of the remaining development works by competent authority or by the association of allottees or any other manner as may be determined by the Authority. The development work has to be completed and cannot be left in between. Section 8 reads thus;


“8. Obligation of Authority consequent upon lapse of or on revocation of registration.- Upon lapse of the registration or on revocation of the registration under this Act, the Authority, may consult the appropriate Government to take such action as it may deem fit including the carrying out of the remaining development works by competent authority or by the association of allottees or in any other manner, as may be determined by the Authority:

Provided that no direction, decision or order of the Authority under this section shall take effect until the expiry of the period of appeal provided under the provisions of this Act:

Provided further that in case of revocation of registration of a project under this Act, the association of allottees shall have the first right of refusal for carrying out of the remaining development works.”