In the Matter of Pioneer Urban Land and Infrastructure Ltd. v. Govindan Raghavan 2019 (5) SCC 725,
The Hon'ble Supreme Court has laid down that the courts will not enforce and will, when called upon to do so, strike down an unfair and unreasonable contract, or an unfair and unreasonable clause in a contract, entered into between the parties, who are not equal in bargaining power. A term of a contract will not be final and binding if it is shown that the flat purchaser had no option but to sign on the dotted line, on a contract framed by a builder. Further, incorporation of one-sided clauses in an agreement constitutes an unfair trade practice since it adopts unfair methods or practices for the purpose of selling the flat by the builder.
In the said case, the Buyer had deposited Rs. 4,83,25,280/- with the Builder for purchase of a flat in Araya Complex, Gurugram (the ‘Flat’), but the Builder had failed to obtain the occupancy certificate within the stipulated time period of 39 months with a grace period of 180 days and therefore, could not offer possession of the Flat to the Buyer within the time period agreed by them vide Agreement dated 08.05.2012.As a result, the Buyer had approached the National Consumer Disputes Redressal Commission (NCDRC), whereby the NCDRC directed the Builder to pay compensation to the Buyer and also awarded interest for a part of the period of delay, vide Order dated 23.10.2018.Meanwhile, the Builder obtained the Occupancy Certificate on 23.07.2018 and issued a Possession Letter to the Buyer on 28.08.2018. But the Buyer refused to accept the same as they were no longer interested to buy the said Flat and were looking for a flat elsewhere. Aggrieved by the Order dated 23.10.2018 of the NCDRC, the Builder filed an appeal before the Supreme Court (‘Appeal’).
x
The Supreme Court held that terms of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. It further held that incorporation of one-sided clauses in an agreement constitutes an unfair trade practice as per Section 2 (r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the builder. The supreme court further added that The Builder cannot compel the Buyer to purchase the Flat after causing an inordinate delay of almost 3 years in handing over the possession of the Flat to the Buyer and the builder cannot seek to bind the Buyer with one-sided and unfair contractual terms of the Agreement.
Thus, the Apex Court directed the Builder to pay compensation and interest to the Buyer for the entire period of delay caused in handing over possession of the Flat to the Buyer.
The Apex court also was of view that “ It is difficult to accept the argument that RERA is a special enactment which deals with real estate development projects and must therefore be given precedence over the Code which is only a general enactment. At the time of introduction of the explanation to Section 5(8)(f) of the IBC, Parliament was aware of RERA and applied some of the definition provisions to the Code.” It also held that “The fact that RERA is in addition to and not in derogation of other laws (Section 88) makes it clear that remedies under RERA to allottees were intended to be additional and not exclusive remedies”.
The Supreme court was of view that “By the process of harmonious construction, RERA and Code must be held to co-exist and in the event of a clash, RERA must give way to the Code. RERA therefore cannot be held to be a special statute which in the case of a conflict, would override the general statute viz. the Code.”