Search This Blog

Translate the Site.

Saturday, 10 August 2024

Legal Maxim: Functus Officio

Legal maxim: Functus Officio

"Functus officio" is a Latin term meaning "having performed his or her office."

 In legal contexts, it signifies that an officer or official body no longer has further authority or legal competence because their original duties and functions have been fully accomplished.

For Example: A trial where a judge presides over a civil case. After the trial concludes, the judge renders a judgment, settling the dispute between the parties. Once the judgment is given, the judge becomes "functus officio." This means that the judge's authority to make changes to the decision ends.

Any further modifications or challenges to the judgment must be pursued through the appellate process, where other judges preside in higher courts of appeal.

Friday, 9 August 2024

A GPA (General Power of Attorney) holder can file a criminal case on behalf of the principal

A GPA (General Power of Attorney) holder can file a criminal case on behalf of the principal (the person who executed the GPA) in certain circumstances. Here are some citations:


Important case laws of Supreme Court:


  1. "R. Rajagopal vs. C.J. Aravindan" (2003): The SC held that a GPA holder can file a criminal complaint on behalf of the principal
  2. M/s. Haryana Telecom Ltd. vs. State of Haryana" (2011): The SC ruled that a GPA holder can file a criminal case, but the principal must be examined as a witness.


Important case laws of High Courts:


  1. "Santosh Kumar Singh vs. State of Bihar" (2012) - Patna High Court: The court held that a GPA holder can file a criminal complaint, but must obtain prior permission from the Magistrate.
  2. K. Srinivas vs. State of A.P." (2015) - Andhra Pradesh High Court: The court ruled that a GPA holder can file a criminal case, but the principal's statement must be recorded under Section 200 CrPC.


Thursday, 1 August 2024

MahaRERA - To ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.

 MahaRERA - To ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.


Anil Kumar Dattani Versus Real Gem Buildtech Private Limited & Ors. Complaint No. CC006000000292852 Before the Maharashtra Real Estate Regulatory Authority Mumbai Decided on 13th May 2024)


Fact of the Case :-

  • Respondent no. 1 i.e. Realgem Buildtech Private Limited  is the Promoter of the project.
  • Respondent no. 2 i.e. Bhishma Realty Limited is the landowner of the project.
  • Respondent no. 3 i.e Kindmaker Developers Private Limited  has been appointed as a Development Manager under the development management agreement dated 18-03-2018 and is basically an agent of the respondent no. 1 functioning for a fixed fee. the respondent no. 3 was appointed for the purposes of 
    • inter alia managing, 
    • monitoring, 
    • supervising and 
    • coordinating the construction and 
    • development of the said project 
    • together with the sales and marketing related activities including customer relationship management.

  • The subject matter of the case is flat bearing no. 2302 on 23rd floor in the “RUSTOMJEE CROWN - PHASE I" at Prabhadevi, Mumbai.
  • On 16-01-2019 The respondent issued  the allotment letter in the complainant's name. 
  • On 25-01-2019 The complainant and the respondents entered into a registered agreement for sale.
  • The respondent had assured to handover the possession of the said flat on 31-12-2021.
  • The Flat was for a total consideration of Rs. 7,69,86,000/-
  • The Complainant has already paid Rs. 7,41,83,995/- to the respondents from time to time..
  • The respondent did not give the possession by the said date.
  • On 27-09-2022 the complainant filed the present complaint..

Submissions by Appellant:-

  • As per the RERA, the all 3 respondents are jointly and severally liable as per circular no. 12/2017 dated 04-12-2017.

Submissions by Respondent(s):

  • The date of possession mentioned in the agreement for sale is 31-12-2021 and the same was subject to provisions of clause 8 of the said agreement which provides for a reasonable extension on occurrence of mitigating events.
  • The Covid 19 pandemic was a force majeure event and therefore covered under clause 8 of the agreement for sale. 

Observations made by the Hon’ble Court:-

  • the Respondent nos. 1 and 2 being the promoters of this project registered with the MahaRERA are liable to perform their part as stipulated in the registered agreement for sale dated 25-01-2019 signed with the complainant herein.
  • With regards to respondent taking the plea on the issue of jurisdiction as per clause 16.1 of the said agreement for sale wheras the complainant has agreed for arbitration in case of any dispute arising in respect of the said agreement for sale.MahaRERA is of the view that the same is raised at a belated stage by filing its reply on record of MahaRERA,
  • Further, there are no explicit provisions under RERA about the arbitration clause. Hence,the same stands rejected.
  • As far as the issue raised by the complainant about GST input credit not being provided to him, the MahaRERA is of the prima facie view that the same does not fall within the purview of the MahaRERA under the provisions of the RERA. 
  • However, it is for the concerned competent forum to deal with such issues. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST. 
  • The MahaRERA is not going to deal with the said issue for want of jurisdiction.
  • the MahaRERA is of the view that the delay cited by the respondent such as delay in obtaining CFO NOC due to change in fire norms and the delay in obtaining NOC from MPCB do not fall within the force majeure factors mentioned in the draft model agreement for sale prescribed under the RERA and the relevant rules made thereunder.

Court’s Order:-

  • The respondent promoter is directed to pay interest for the delayed possession to the complainants from 01-01-2023 ( as per agreements for sale i.e. 31-12-2021 + 1 year grace period due to Covid-19 Pandemic i.e. 31-12-2022) for every month till the actual date of possession of the said flat to the complainant or till the date of offer of possession with OC if any obtained by the respondent promoter. 
  • to ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.

MAHA RERA - The delay in obtaining NOCs including Fire NOC do not fall within the force majeure factors prescribed under the RERA and the relevant rules made thereunder.

 MAHA RERA - The delay in obtaining NOCs  including Fire NOC do not fall within the force majeure factors prescribed under the RERA and the relevant rules made thereunder.


Anil Kumar Dattani Versus Real Gem Buildtech Private Limited & Ors. Complaint No. CC006000000292852 Before the Maharashtra Real Estate Regulatory Authority Mumbai Decided on 13th May 2024)


Fact of the Case :-

  • Respondent no. 1 i.e. Realgem Buildtech Private Limited  is the Promoter of the project.
  • Respondent no. 2 i.e. Bhishma Realty Limited is the landowner of the project.
  • Respondent no. 3 i.e Kindmaker Developers Private Limited  has been appointed as a Development Manager under the development management agreement dated 18-03-2018 and is basically an agent of the respondent no. 1 functioning for a fixed fee. the respondent no. 3 was appointed for the purposes of 
    • inter alia managing, 
    • monitoring, 
    • supervising and 
    • coordinating the construction and 
    • development of the said project 
    • together with the sales and marketing related activities including customer relationship management.

  • The subject matter of the case is flat bearing no. 2302 on 23rd floor in the “RUSTOMJEE CROWN - PHASE I" at Prabhadevi, Mumbai.
  • On 16-01-2019 The respondent issued  the allotment letter in the complainant's name. 
  • On 25-01-2019 The complainant and the respondents entered into a registered agreement for sale.
  • The respondent had assured to handover the possession of the said flat on 31-12-2021.
  • The Flat was for a total consideration of Rs. 7,69,86,000/-
  • The Complainant has already paid Rs. 7,41,83,995/- to the respondents from time to time..
  • The respondent did not give the possession by the said date.
  • On 27-09-2022 the complainant filed the present complaint..

Submissions by Appellant:-

  • As per the RERA, the all 3 respondents are jointly and severally liable as per circular no. 12/2017 dated 04-12-2017.

Submissions by Respondent(s):

  • The date of possession mentioned in the agreement for sale is 31-12-2021 and the same was subject to provisions of clause 8 of the said agreement which provides for a reasonable extension on occurrence of mitigating events.
  • The Covid 19 pandemic was a force majeure event and therefore covered under clause 8 of the agreement for sale. 

Observations made by the Hon’ble Court:-

  • the Respondent nos. 1 and 2 being the promoters of this project registered with the MahaRERA are liable to perform their part as stipulated in the registered agreement for sale dated 25-01-2019 signed with the complainant herein.
  • With regards to respondent taking the plea on the issue of jurisdiction as per clause 16.1 of the said agreement for sale wheras the complainant has agreed for arbitration in case of any dispute arising in respect of the said agreement for sale.MahaRERA is of the view that the same is raised at a belated stage by filing its reply on record of MahaRERA,
  • Further, there are no explicit provisions under RERA about the arbitration clause. Hence,the same stands rejected.
  • As far as the issue raised by the complainant about GST input credit not being provided to him, the MahaRERA is of the prima facie view that the same does not fall within the purview of the MahaRERA under the provisions of the RERA. 
  • However, it is for the concerned competent forum to deal with such issues. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST. 
  • The MahaRERA is not going to deal with the said issue for want of jurisdiction.
  • the MahaRERA is of the view that the delay cited by the respondent such as delay in obtaining CFO NOC due to change in fire norms and the delay in obtaining NOC from MPCB do not fall within the force majeure factors mentioned in the draft model agreement for sale prescribed under the RERA and the relevant rules made thereunder.

Court’s Order:-

  • The respondent promoter is directed to pay interest for the delayed possession to the complainants from 01-01-2023 ( as per agreements for sale i.e. 31-12-2021 + 1 year grace period due to Covid-19 Pandemic i.e. 31-12-2022) for every month till the actual date of possession of the said flat to the complainant or till the date of offer of possession with OC if any obtained by the respondent promoter. 
  • to ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.

Maha RERA - Issue of GST input credit does not fall within the purview of the provisions of the RERA. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST.

Issue of  GST input credit does not fall within the purview of the  provisions of the RERA. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST.  


Anil Kumar Dattani Versus Real Gem Buildtech Private Limited & Ors. Complaint No. CC006000000292852 Before the Maharashtra Real Estate Regulatory Authority Mumbai Decided on 13th May 2024)


Fact of the Case :-

  • Respondent no. 1 i.e. Realgem Buildtech Private Limited  is the Promoter of the project.
  • Respondent no. 2 i.e. Bhishma Realty Limited is the landowner of the project.
  • Respondent no. 3 i.e Kindmaker Developers Private Limited  has been appointed as a Development Manager under the development management agreement dated 18-03-2018 and is basically an agent of the respondent no. 1 functioning for a fixed fee. the respondent no. 3 was appointed for the purposes of 
    • inter alia managing, 
    • monitoring, 
    • supervising and 
    • coordinating the construction and 
    • development of the said project 
    • together with the sales and marketing related activities including customer relationship management.

  • The subject matter of the case is flat bearing no. 2302 on 23rd floor in the “RUSTOMJEE CROWN - PHASE I" at Prabhadevi, Mumbai.
  • On 16-01-2019 The respondent issued  the allotment letter in the complainant's name. 
  • On 25-01-2019 The complainant and the respondents entered into a registered agreement for sale.
  • The respondent had assured to handover the possession of the said flat on 31-12-2021.
  • The Flat was for a total consideration of Rs. 7,69,86,000/-
  • The Complainant has already paid Rs. 7,41,83,995/- to the respondents from time to time..
  • The respondent did not give the possession by the said date.
  • On 27-09-2022 the complainant filed the present complaint..

Submissions by Appellant:-

  • As per the RERA, the all 3 respondents are jointly and severally liable as per circular no. 12/2017 dated 04-12-2017.

Submissions by Respondent(s):

  • The date of possession mentioned in the agreement for sale is 31-12-2021 and the same was subject to provisions of clause 8 of the said agreement which provides for a reasonable extension on occurrence of mitigating events.
  • The Covid 19 pandemic was a force majeure event and therefore covered under clause 8 of the agreement for sale. 

Observations made by the Hon’ble Court:-

  • the Respondent nos. 1 and 2 being the promoters of this project registered with the MahaRERA are liable to perform their part as stipulated in the registered agreement for sale dated 25-01-2019 signed with the complainant herein.
  • With regards to respondent taking the plea on the issue of jurisdiction as per clause 16.1 of the said agreement for sale wheras the complainant has agreed for arbitration in case of any dispute arising in respect of the said agreement for sale.MahaRERA is of the view that the same is raised at a belated stage by filing its reply on record of MahaRERA,
  • Further, there are no explicit provisions under RERA about the arbitration clause. Hence,the same stands rejected.
  • As far as the issue raised by the complainant about GST input credit not being provided to him, the MahaRERA is of the prima facie view that the same does not fall within the purview of the MahaRERA under the provisions of the RERA. 
  • However, it is for the concerned competent forum to deal with such issues. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST. 
  • The MahaRERA is not going to deal with the said issue for want of jurisdiction.
  • the MahaRERA is of the view that the delay cited by the respondent such as delay in obtaining CFO NOC due to change in fire norms and the delay in obtaining NOC from MPCB do not fall within the force majeure factors mentioned in the draft model agreement for sale prescribed under the RERA and the relevant rules made thereunder.

Court’s Order:-

  • The respondent promoter is directed to pay interest for the delayed possession to the complainants from 01-01-2023 ( as per agreements for sale i.e. 31-12-2021 + 1 year grace period due to Covid-19 Pandemic i.e. 31-12-2022) for every month till the actual date of possession of the said flat to the complainant or till the date of offer of possession with OC if any obtained by the respondent promoter. 
  • to ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.

Maha RERA - There are no explicit provisions under RERA about the arbitration clause in agreement for Sale

There are no explicit provisions under RERA about the arbitration clause in agreement for Sale 

Anil Kumar Dattani Versus Real Gem Buildtech Private Limited & Ors. Complaint No. CC006000000292852 Before the Maharashtra Real Estate Regulatory Authority Mumbai Decided on 13th May 2024)


Fact of the Case :-

  • Respondent no. 1 i.e. Realgem Buildtech Private Limited  is the Promoter of the project.
  • Respondent no. 2 i.e. Bhishma Realty Limited is the landowner of the project.
  • Respondent no. 3 i.e Kindmaker Developers Private Limited  has been appointed as a Development Manager under the development management agreement dated 18-03-2018 and is basically an agent of the respondent no. 1 functioning for a fixed fee. the respondent no. 3 was appointed for the purposes of 
    • inter alia managing, 
    • monitoring, 
    • supervising and 
    • coordinating the construction and 
    • development of the said project 
    • together with the sales and marketing related activities including customer relationship management.

  • The subject matter of the case is flat bearing no. 2302 on 23rd floor in the “RUSTOMJEE CROWN - PHASE I" at Prabhadevi, Mumbai.
  • On 16-01-2019 The respondent issued  the allotment letter in the complainant's name. 
  • On 25-01-2019 The complainant and the respondents entered into a registered agreement for sale.
  • The respondent had assured to handover the possession of the said flat on 31-12-2021.
  • The Flat was for a total consideration of Rs. 7,69,86,000/-
  • The Complainant has already paid Rs. 7,41,83,995/- to the respondents from time to time..
  • The respondent did not give the possession by the said date.
  • On 27-09-2022 the complainant filed the present complaint..

Submissions by Appellant:-

  • As per the RERA, the all 3 respondents are jointly and severally liable as per circular no. 12/2017 dated 04-12-2017.

Submissions by Respondent(s):

  • The date of possession mentioned in the agreement for sale is 31-12-2021 and the same was subject to provisions of clause 8 of the said agreement which provides for a reasonable extension on occurrence of mitigating events.
  • The Covid 19 pandemic was a force majeure event and therefore covered under clause 8 of the agreement for sale. 

Observations made by the Hon’ble Court:-

  • the Respondent nos. 1 and 2 being the promoters of this project registered with the MahaRERA are liable to perform their part as stipulated in the registered agreement for sale dated 25-01-2019 signed with the complainant herein.
  • With regards to respondent taking the plea on the issue of jurisdiction as per clause 16.1 of the said agreement for sale wheras the complainant has agreed for arbitration in case of any dispute arising in respect of the said agreement for sale.MahaRERA is of the view that the same is raised at a belated stage by filing its reply on record of MahaRERA,
  • Further, there are no explicit provisions under RERA about the arbitration clause. Hence,the same stands rejected.
  • As far as the issue raised by the complainant about GST input credit not being provided to him, the MahaRERA is of the prima facie view that the same does not fall within the purview of the MahaRERA under the provisions of the RERA. 
  • However, it is for the concerned competent forum to deal with such issues. Hence, the complainant need to approach the appropriate forum for redressal of the said grievances about the GST. 
  • The MahaRERA is not going to deal with the said issue for want of jurisdiction.
  • the MahaRERA is of the view that the delay cited by the respondent such as delay in obtaining CFO NOC due to change in fire norms and the delay in obtaining NOC from MPCB do not fall within the force majeure factors mentioned in the draft model agreement for sale prescribed under the RERA and the relevant rules made thereunder.

Court’s Order:-

  • The respondent promoter is directed to pay interest for the delayed possession to the complainants from 01-01-2023 ( as per agreements for sale i.e. 31-12-2021 + 1 year grace period due to Covid-19 Pandemic i.e. 31-12-2022) for every month till the actual date of possession of the said flat to the complainant or till the date of offer of possession with OC if any obtained by the respondent promoter. 
  • to ensure that the said project is not jeopardized due to the outflow of finances it is directed that the amounts of interest shall be paid by the respondent promoter to the said complainants after obtaining the full occupancy certificate.

Supreme Court of India - The power to supersede the authority is entrusted to the appropriate Government in terms of Section 82.

Supreme Court of India - The power to supersede the authority is entrusted to the appropriate Government in terms of Section 82.


Facts:-

  • On 5 January 2024, one of the members of RERA superannuated.
  • On 7 February 2024, the Chairperson resigned without giving notice of three months and the resignation was accepted immediately by the state Government.
  • with effect from 10 March 2024, the remaining member of RERA proceeded on leave for a period of three months until 6 June 2024.
  • On 9 March 2024, the State Government in the Department of Housing and Urban Development issued notice to the Authority proposing to supersede the Authority.
  • On 12 March 2024, the State Government issued an order under Section 82(1) superseding the Authority.

  • On 13 March 2024, the Government  appointed Shri M S Jaggi, IAS to exercise the powers and discharge the functions of the Authority under the Act in terms of the provisions of Section 82(1).

PIL in Punjab & Haryana High Court :-

  • A Public Interest Litigation KEERTI SANDHU & ORS. V/s  STATE OF PUNJAB & ANR.CWP-(PIL) No. 48/2024  was moved before the High Court of Punjab & Haryana in which the order dated 14 March 2024 was passed by a Division Bench, where it noted that the authority has to exercise sensitive functions including permissions to be given to builders and dealing with complaints against builders and hence it is not in the interest of justice if the supersession is allowed at that point of time. Consequently, the order of the Government dated 12 March 2024 was stayed by the High Court.

Appeal in the Supreme Court of India :- 


  • An appeal was preferred by the state in the matter of STATE OF PUNJAB & ANR. V/s KEERTI SANDHU & ORS.7152/2024 where the supreme court of india set aside the impugned order dated 14 March 2024 of the High Court.
  • It also held that The power to supersede the authority is entrusted to the appropriate Government in terms of Section 82. 
  • It also noted that The order of the High Court staying the notification of the State Government dated 12 March 2024 would not advance the purpose and object of the statute. 
  • A stay on the supersession cannot either bring back the member who has superannuated or restore the Chairperson who has tendered his resignation.